35 Ill. Adm. Code 104.204
Petition Content Requirements
Section 104
Section 104.204Â Petition
Content Requirements
The petition must include the
information required by subsections (a) through (n). Additionally, there are
specific content requirements set forth at Section 104.206 for RCRA variance
petitions. If the petitioner believes that any of these requirements are not
applicable to the specific variance requested, the petitioner must so state and
explain the reasoning.
a)Â Â Â Â Â Â Â Â A statement describing the regulation, requirement, or order
of the Board from which a variance is sought. If variance from a regulation is
sought, the statement must include the Illinois Administrative Code citation to
the regulation as well as the effective date of that regulation. If variance
from a requirement or order of the Board is sought, the statement must include
the citation to that requirement or order of the Board promulgating that
requirement, including docket number;
b)Â Â Â Â Â Â Â Â A complete and concise description of the nature of
petitioner's activity that is the subject of the proposed variance, including:
1)Â Â Â Â Â Â Â Â The location of, and area affected by, the petitioner's
activity;
2)Â Â Â Â Â Â Â Â The location of points of discharge, and, as applicable, the
identification of the receiving waterway or land, or, if known, the location of
the nearest air monitoring station maintained by the Agency;
3)Â Â Â Â Â Â Â Â An identification, including docket number, of any prior
variance issued to the petitioner and, if known, the petitioner's predecessors,
concerning similar relief;
4)Â Â Â Â Â Â Â Â An identification, including number, of the environmental
permits held by petitioner for the activity which may be affected by grant of
variance;
5)Â Â Â Â Â Â Â Â The number of persons employed by the petitioner's facility at
issue and the age of that facility;
6)Â Â Â Â Â Â Â Â The nature and amount of the materials used in the process or
activity for which the variance is sought and a full description of the
particular process or activity in which the materials are used;
7)Â Â Â Â Â Â Â Â A description of the relevant pollution control equipment
already in use; and
8)Â Â Â Â Â Â Â Â The nature and amount of emissions, discharges or releases of
the constituent in question currently generated by the petitioner's activity;
c)Â Â Â Â Â Â Â Â Data describing the nature and extent of the present or
anticipated failure to meet the regulation, requirement, or order of the Board
from which variance is sought and facts that support petitioner's argument that
compliance with the regulation, requirement, or order of the Board was not or
cannot be achieved by any required compliance date;
d)Â Â Â Â Â Â Â Â A description of the efforts that would be necessary for the
petitioner to achieve immediate compliance with the regulation, requirement, or
Board order at issue. All possible compliance alternatives, with the
corresponding costs for each alternative, must be set forth and discussed. The
discussion of compliance alternatives must include the availability of
alternate methods of compliance, the extent that the methods were studied, and
the comparative factors leading to the selection of the control program
proposed for compliance. The discussion of the costs of immediate compliance
may include the overall capital costs and the annualized capital and operating
costs;
e)Â Â Â Â Â Â Â Â Facts that set forth the reasons the petitioner believes that
immediate compliance with the regulation, requirement, or order of the Board
would impose an arbitrary or unreasonable hardship;
f)Â Â Â Â Â Â Â Â A detailed description of the compliance plan, including:
1)Â Â Â Â Â Â Â Â A discussion of the proposed equipment or proposed method of
control to be undertaken to achieve full compliance with the regulation,
requirement, or order of the Board;
2)Â Â Â Â Â Â Â Â A time schedule for the implementation of all phases of the
control program from initiation of design to program completion; and
3)Â Â Â Â Â Â Â Â The estimated costs involved for each phase and the total cost
to achieve compliance;
g)Â Â Â Â Â Â Â Â A description of the environmental impact of the petitioner's
activity including:
1)Â Â Â Â Â Â Â Â The nature and amount of emissions, discharges, or releases of
the constituent in question if the requested variance is granted, compared to
that which would result if immediate compliance is required;
2)Â Â Â Â Â Â Â Â The qualitative and quantitative description of the impact of
petitioner's activity on human health and the environment if the requested
variance is granted, compared to the impact of petitioner's activity if
immediate compliance is required. Cross-media impacts, if any, must be
discussed; and
3)Â Â Â Â Â Â Â Â A statement of the measures to be undertaken during the period
of the variance to minimize the impact of the discharge of contaminants on
human, plant, and animal life in the affected area, including the numerical
interim discharge limitations that can be achieved during the period of the
variance;
h)Â Â Â Â Â Â Â Â Citation to supporting documents or legal authorities whenever
they are used as a basis for the petition. Relevant portions of the documents
and legal authorities other than Board decisions, reported state and federal
court decisions, or state and federal regulations and statutes must be appended
to the petition;
i)Â Â Â Â Â Â Â Â Â If the requested variance involves an existing permit or a
pending permit application, a copy of the material portion of the permit or
permit application must be appended to the petition;
j)Â Â Â Â Â Â Â Â Â Any conditions petitioner suggests for the requested
variance;
k)        A proposed beginning and ending date for the variance. If the
petitioner requests that the term of the variance begin on any date other than
the date on which the Board takes final action on the petition, a detailed
explanation and justification for the alternative beginning date;
l)Â Â Â Â Â Â Â Â Â A discussion of consistency with federal law, including an
analysis of applicable federal law and facts that may be necessary to show
compliance with federal law as set forth in Section 104.208;
m)Â Â Â Â Â Â Â An affidavit verifying any facts submitted in the petition; and
n)Â Â Â Â Â Â Â Â A statement requesting or denying that a hearing should be
held in this matter.