35 Ill. Adm. Code 1100.205
Certifications and Load Checking
Section 1100.205Â Certifications and Load Checking
a)Â Â Â Â Â Â Â Â The
owner or operator must do all of the following activities and document all the
activities for all CCDD and uncontaminated soil accepted for use as fill
material:
1)Â Â Â Â Â Â Â Â For all
soil, including soil mixed with CCDD, obtain:
A)Â Â Â Â Â Â Â a
certification from the source site owner or source site operator that the site
is not a potentially impacted property and is presumed to be uncontaminated
soil, and soil pH is within the range of 6.25 to 9.0. A certification under
this subsection (a)(1)(A) must include soil pH testing results to show that the
soil pH is within the range of 6.25 to 9.0. Â If soil is consolidated from more
than one source site, a certification must be obtained from each source site
owner or source site operator; or
B)Â Â Â Â Â Â Â a
certification from a PE or PG that the soil is uncontaminated soil,
and
the soil pH is within the range of 6.25 to 9.0. A certification under this
subsection (a)(1)(B) must include analytical soil testing results to show that
soil chemical constituents comply with the maximum allowable concentrations
established pursuant to Subpart F of this Part, and the soil pH is within the
range of 6.25 to 9.0.
2)Â Â Â Â Â Â Â Â Certifications
required under subsections (a)(1)(A) and (a)(1)(B) must be on forms and in a
format prescribed by the Agency and must provide, at a minimum:
A)Â Â Â Â Â Â Â For
source site owners or source site operators who certify under subsection
(a)(1)(A), the form must provide, at a minimum:
i)Â Â Â Â Â Â Â Â Â Description
of the current and past uses of the site where the soil originated, giving
consideration to, but not limited to: use of the site for commercial or
industrial purposes; presence of any storage tanks (aboveground or underground)
being located on the site; use of the site for waste treatment or disposal; any
governmental notification of environmental violations pertaining to the site;
any contamination in any private wells on site that exceeds the Board's
groundwater quality standards; any transformers or capacitors manufactured
before 1979 being used, stored, or disposed of on the site; and any fill dirt
used at the site from either an unknown source or a site;
ii)Â Â Â Â Â Â Â Â Soil
pH testing results to show that the soil pH is within the range of 6.25 to 9.0;
iii)Â Â Â Â Â Â Â A
certification using the following language:Â In accordance with the
Environmental Protection Act [415 ILCS 5/22.51 or 22.51a] and 35 Ill. Adm. Code
1100.205(a), I __________ (owner or operator of source site) certify that this
site is not a potentially impacted property and the soil is presumed to be
uncontaminated soil. I also certify that the soil pH is within the range of
6.25 to 9.0. Additionally, I certify that I am either the site owner or site
operator or a duly authorized representative of the site owner or site operator
and am authorized to sign this form. Furthermore, I certify that all
information submitted, including but not limited to all attachments and other
information, is, to the best of my knowledge and belief, true, accurate and
complete.
B)Â Â Â Â Â Â Â For PE
or PG who certify under subsection (a)(1)(B), the following language:Â I
________ (name of licensed professional engineer or geologist) certify under
penalty of law that the information submitted, including but not limited to all
attachments and other information, is, to the best of my knowledge and belief,
true, accurate and complete. In accordance with the Environmental Protection
Act [415 ILCS 5/22.51 or 22.51a] and 35 Ill. Adm. Code 1100.205(a), I certify
that the soil from this site is uncontaminated soil. I also certify that the
soil pH is within the range of 6.25 to 9.0. All necessary documentation is
attached.
3)Â Â Â Â Â Â Â Â Confirm
and document that the CCDD or uncontaminated soil was not removed from a site
as part of a cleanup or removal of contaminants, including, but not limited to,
activities conducted under the Comprehensive Environmental Response,
Compensation, and Liability Act of 1980, as amended, as part of a Closure or
Corrective Action under the Resource Conservation and Recovery Act, as amended,
or under an Agency remediation program, such as the Leaking Underground Storage
Tank Program or Site Remediation Program, but excluding sites subject to
Section 58.16 of the Act when there is no presence or likely presence of a
release or a substantial threat of a release of a regulated substance at, on, or
from the real property.
4)Â Â Â Â Â Â Â Â For
all testing conducted to determine that the soil is uncontaminated, obtain
documentation to show that the soil was tested in accordance with the
requirements of Subpart F of this Part.
5)Â Â Â Â Â Â Â Â Obtain
documentation on rejected loads.
A)Â Â Â Â Â Â Â For
loads rejected from the same or another fill operation, the owner or operator
may accept a rejected load if subsections (a)(1) through (a)(4) are satisfied
and the owner or operator also obtains the following information:
i)Â Â Â Â Â Â Â Â Â Information
identifying the rejected load and the reasons it was rejected, including, but
not limited to, a copy of the written notice the driver received pursuant to
subsection (b)(4)(A) of this Section when the load was rejected;
ii)Â Â Â Â Â Â Â Â Information
demonstrating that the load proposed for acceptance is the rejected load
identified in this subsection (a)(5);
iii)Â Â Â Â Â Â Â Information
demonstrating that the reasons for rejection of the load have been addressed by
measures that would include, but not be limited to, testing and retesting of
soils or removal of nonconforming materials; and
iv)Â Â Â Â Â Â Â For
all soil, including soil mixed with CCDD, a certification meeting the
requirements of subsection (a)(1) of this Section that is executed after
correction of the reasons for the load rejection. This subsection (a)(5)(A)(iv)
does not apply if load rejection was due to the detection of non-CCDD or
non-soil material, including, but not limited to, wood, glass, piping,
vegetation, plastic, metal, electrical wiring, or concrete with protruding
rebar.
B)Â Â Â Â Â Â Â Except
as provided in subsection (a)(5)(A)(iv), the information required under this subsection
(a)(5) must be on forms and in a format prescribed by the Agency, and must be
certified by the source site owner, the source site operator, a PE or PG.Â
Loads accepted pursuant to this subsection (a)(5) are subject to all other
requirements of this Part, including, but not limited to, the load checking
program in effect at the receiving fill operation (see subsection (b)).
b)Â Â Â Â Â Â Â Â The
owner or operator must institute and conduct a load checking program designed
to detect attempts to dispose of waste
at the
facility. At a minimum, the load checking program must consist of the
following components:
1)Â Â Â Â Â Â Â Â Routine
Inspections
A)Â Â Â Â Â Â Â An
inspector designated by the facility must inspect every load before its
acceptance at the facility utilizing an elevated structure, a designated ground
level inspection area, or another acceptable method as specified in the Agency
permit. In addition to a visual inspection, the inspector must use an
instrument with a photo ionization detector utilizing a lamp of 10.6 eV or
greater or an instrument with a flame ionization detector, or other monitoring
devices approved by the Agency, to inspect each load. All instruments shall be
interpreted based on the manufacturer's margin of error. Any reading in excess
of background levels using any of these instruments must result in the
rejection of the inspected load. In addition, any reading in excess of
background levels on any monitoring device used by the Agency during an Agency
inspection must result in the rejection of the inspected load.
B)Â Â Â Â Â Â Â Cameras
or other devices may be used to record the visible contents of shipments.Â
Where such devices are employed, their use should be designated on a sign
posted near the entrance to the facility.
2)Â Â Â Â Â Â Â Â Random
Inspections
A)Â Â Â Â Â Â Â In
addition to the inspections required under subsection (b)(1), an inspector
designated by the facility must conduct a discharge inspection of at least one
randomly selected load delivered to the facility each day. The driver of the
randomly selected load must be directed to discharge the load at a separate,
designated location within the facility. The inspector must conduct an
inspection of the discharged material that includes, but is not limited to,
additional visual inspection and additional instrument testing using the
instruments required under subsection (b). All instruments shall be
interpreted based on the manufacturer's margin of error. Any reading in excess
of background levels using any of these instruments must result in the
rejection of the inspected load. In addition, any reading in excess of
background levels on any monitoring device used by the Agency during an Agency
inspection must result in the rejection of the inspected load.
B)Â Â Â Â Â Â Â Cameras
or other devices may be used to record the visible contents of shipments.Â
Where such devices are employed, their use should be designated on a sign
posted near the entrance to the facility.
3)Â Â Â Â Â Â Â Â Documentation
of Inspection Results: Â The documentation for each inspection must include, at
a minimum, the following:
A)Â Â Â Â Â Â Â The
date and time of the inspection, the date the CCDD or uncontaminated soil was
received, the weight or volume of the CCDD or uncontaminated soil, the name of
the hauler, the name of the hauling firm, the vehicle identification number or
license plate number, the source site owner and source site operator, and the location
of the site of origin of the CCDD or uncontaminated soil;
B)Â Â Â Â Â Â Â The
results of the routine inspection required under subsection (b)(1) of this
Section, including, but not limited to, the monitoring instruments used,
whether the load was accepted or rejected, and for rejected loads the reason
for the rejection;
C)Â Â Â Â Â Â Â The results
of any random inspection required under subsection (b)(2) of this Section,
including, but not limited to, the monitoring instruments used, whether the
load was accepted or rejected, and for rejected loads the reason for the
rejection; and
D)Â Â Â Â Â Â Â The name
of the inspector.
4)Â Â Â Â Â Â Â Â Rejection
of Loads
A)Â Â Â Â Â Â Â If
material other than CCDD or uncontaminated soil is found or suspected, the
owner or operator must reject the load and present the driver of the rejected
load with written notice of the following:
i)Â Â Â Â Â Â Â Â Â That
only CCDD or uncontaminated soil is accepted for use as fill at the facility;
ii)Â Â Â Â Â Â Â Â The
reasons for rejections of the load, that the material must not be taken to
another fill operation, except as provided in subsection (b)(4)(A)(iv) or the
material must be disposed of at a permitted landfill;
iii)Â Â Â Â Â Â Â That,
for all inspected loads, the owner or operator is required to record and make
available for Agency inspection, at a minimum, the date and time of the
inspection, the weight or volume of the CCDD or uncontaminated soil, the name
of the hauler, the name of the hauling firm, the vehicle identification number
or license plate number, the source site owner and source site operator, and
the location of the site of origin of the fill; and
iv)Â Â Â Â Â Â Â That
a load rejected from a fill operation may be accepted by the same fill
operation or another fill operation if the requirements of subsection (a)(5)
are satisfied.
B)Â Â Â Â Â Â Â The
owner or operator must ensure the cleanup, transportation, and proper disposal
of any material other than CCDD or uncontaminated soil that remains at the
facility after the rejection of a load.
5)Â Â Â Â Â Â Â Â The
owner or operator must take special precautionary measures prior to accepting
loads from persons or sources found or suspected to be responsible for sending
or transporting material other than CCDD or uncontaminated soil to the
facility. The special precautionary measures may include, but are not limited
to, communication with the source site owner or source site operator of the
CCDD or uncontaminated soil, communication with the PE or PG certifying
pursuant to subsection (a)(1)(B), questioning the driver about the load prior
to its discharge, and increased visual inspection and instrument testing of the
load.
6)Â Â Â Â Â Â Â Â If
material other than CCDD or uncontaminated soil is discovered to be improperly
accepted or deposited at the facility, the owner or operator must remove and
properly dispose of the material.
7)Â Â Â Â Â Â Â Â The
owner or operator must ensure that all appropriate facility personnel are
properly trained in the identification of material that is not CCDD or
uncontaminated soil.
8)Â Â Â Â Â Â Â Â All
field measurement activities relative to equipment and instrument operation,
calibration and maintenance and data handling shall be conducted in accordance
with the following:
A)Â Â Â Â Â Â Â "Test
Methods for Evaluating Solid Waste, Physical/Chemical Methods" (SW-846),
Vol. One, Ch. One (Quality Control), incorporated by reference at Section
1100.104;
B)Â Â Â Â Â Â Â The
equipment or instrument manufacturer's or vendor's published standard operating
procedures; or
C)Â Â Â Â Â Â Â Other
operating procedures specified in the Agency permit for CCDD facility or
approved by the Agency in writing for an uncontaminated soil fill operation.
c)Â Â Â Â Â Â Â Â Documentation
required under this Section must be kept for a minimum of 3 years at the
facility or in some alternative location specified in the Agency permit for
CCDD facility, or approved by the Agency in writing for an uncontaminated soil
fill operation. Documentation relating to an appeal, litigation or other
disputed claim must be maintained until at least 3 years after the date of the
final disposition of the appeal, litigation, or other disputed claim. The
documentation must be available for inspection and copying by the Agency and by
units of local government upon request during normal business hours.
d)Â Â Â Â Â Â Â Â For
painted CCDD to be accepted for use as fill material in accordance with Section
1100.212, the owner or operator of the CCDD fill operation must:
1)Â Â Â Â Â Â Â Â Obtain
a certification from a PE or PG that the painted CCDD satisfies the
requirements of Section 1100.212. The certification required under this
subsection (d)(1) must be on forms and in a format prescribed by the Agency.Â
Documentation required by Section 1100.212(c)(2)
must be attached to the
certification form.
2)Â Â Â Â Â Â Â Â Comply
with the load checking requirements of subsection (b).
3)Â Â Â Â Â Â Â Â Comply
with the document retention requirements of subsection (c) for the PE or PG
certification and the attached documentation required under Section 1100.212(c)(2).