35 Ill. Adm. Code 1100.412
Procedures for Closure and Postclosure Maintenance
Section 1100.412 Procedures for Closure and Postclosure
Maintenance
a) Notification of Closure
The owner or operator must provide
written notification of closure to the Agency within 30 days after the date the
owner or operator is deemed to have completed filling under Section 1100.208(a).
b) Certification of Closure
1) When
the closure of the facility is complete, the owner or operator must submit to
the Agency:
A) Documentation
concerning closure of the facility, including, but not limited to, plans or
diagrams of the facility as closed and the date closure was completed.
B) An
affidavit by the owner or operator and the seal of a PE or PG that the facility
has been closed in accordance with the closure plan and the closure
requirements of this Part.
2) When
the Agency determines, pursuant to the information received pursuant to
subsection (b)(1) of this Section and any Agency site inspection, that the
facility has been closed in accordance with the specifications of the closure
plan and the closure requirements of this Part, the Agency must:
A) Issue a certificate of
closure; and
B) Specify
the date the postclosure maintenance period begins, based on the date closure
was completed.
c) Termination of the
Permit
1) At
the end of the postclosure maintenance period, the owner or operator may submit
to the Agency an application for termination of the permit. The application
must be submitted in a format prescribed by the Agency and must include, at a
minimum, the certification of a PE or PG and the affidavit of the owner or
operator demonstrating that, due to compliance with the postclosure maintenance
plan and the postclosure maintenance requirements of this Part, postclosure
maintenance is no longer necessary because:
A) Vegetation has been
established on all nonpaved areas;
B) The
surface has stabilized sufficiently with respect to settling and erosion so
that further stabilization measures, pursuant to the postclosure maintenance
plan, are no longer necessary; and
C) The
owner or operator has completed all requirements of the postclosure maintenance
plan.
2) Within
90 days after receiving the certification required by subsection (c)(1), the
Agency must notify the owner or operator in writing that the permit is
terminated, unless the Agency determines, pursuant to the information received
pursuant to subsection (c)(1) and any Agency site inspection, that continued
postclosure maintenance is required pursuant to the postclosure maintenance
plan and this Part.
3) For
purposes of appeal pursuant to Section 40(d) of the Act and the appeal
provisions of this Part, Agency action pursuant to subsection (c)(2) of this
Section is deemed a denial or grant of permit with conditions.