35 Ill. Adm. Code 201.170
Portable Emission Units
Section
201.170 Portable Emission Units
a) An emission unit is
portable provided that the emission unit meets the following criteria.
1) Emissions from the
emission unit are expected to occur for less than one year at any one site.
2) The emission unit of air
pollution is subject to the requirements of Section 201.169 of this Subpart.
3) The emission unit or
group of emission units that will be changing sites is permitted to emit less
than 25 tons per year of any combination of regulated air pollutants.
4) The
emission unit is mounted on a chassis or skids and is designed to be moveable.
5) The
emission unit is not used as a thermal desorption system pursuant to 35 Ill.
Adm. Code 728.Table F or as an incinerator system.
b) An owner or operator of
a portable emission unit meeting the requirements of subsection (a) of this
Section may change the site of the unit without obtaining a new construction or
operating permit pursuant to Section 201.142, 201.143, or 201.169 of this Part,
provided that the owner or operator meets the following requirements:
1) The owner or operator
has obtained a construction and operating permit containing special conditions
as required by subsection (c) of this Section for the
emission
unit, or is exempt pursuant to subsection (d) of this Section.
2) If a permit issued
pursuant to subsection (c) of this Section includes more than one emission
unit, the owner or operator shall move all emission units covered by the permit
to the new site.
3) The owner or operator
does not locate the emission unit on a site with a source:
A) That
is subject to the requirements of Section 39.5 of the Act; or
B) That would become subject
to the requirements of Section 39.5 of the Act if the emissions of all
regulated pollutants from the portable emission unit were included in such
source’s potential to emit.
4) The owner or operator
does not modify the operation of the emission unit in such a way so as to:
A) Make the emission unit
subject to New Source Review (NSR) requirements pursuant to 35 Ill. Adm. Code
203 or to Prevention of Significant Deterioration (PSD) pursuant to Section
9.1(a) of the Act; or
B) Make the emission unit a
support facility of a source that is subject to Section 39.5 of the Act.
5)
At
least three days
prior to moving the emission unit to a new site, the owner
or operator shall notify the Agency by certified mail.
The notification shall include
the items listed in this
subsection (b)(5), unless the emission unit is exempt pursuant to subsection
(d) of this Section:
A) The location of the new
site;
B) The estimated emissions
of all regulated air pollutants while located at the new site; and
C) That the operation for the
emission unit
will be consistent with its
construction and operating permits.
6) The owner or operator
shall keep a copy of the construction and operating permits for that emission
unit on the site where the emission unit is in operation.
c) Permit Requirements.
1) The owner or operator of
an emission unit must obtain a new or amended construction and operating permit
containing special conditions for changing the site of the portable emission
unit pursuant to the requirements of Sections 201.142, 201.143 and 201.169 of
this Subpart prior to an initial change in site of an emission unit. The permit
application, in addition to the information required pursuant to Section
201.152, 201.157 and 201.169 of this Part, must contain the following
information:
A) The initial site of the
emission unit;
B) A permanent address where
correspondence may be sent to the owner or operator; and
C) The permanent site of any
required operating records.
2) If the portable emission
unit has a permit pursuant to this subsection (c), but has not changed sites
within the prior twelve months at least once, the owner or operator shall
obtain a revised permit prior to changing the site of the emission unit.
d) The owner or operator of
a portable emission unit that is included in more than one operating permit and
meets the requirements of subsections (a)(2) through (a)(5), (b)(3), (b)(4) and
(b)(6) of this Section may change the site of the unit without obtaining a new
construction or operating permit pursuant to Section 201.142, 201.143 or
201.169 of this Part when the unit is moved to a site covered by the permit.