a) A project completion schedule shall contain, as a minimum, the
following data and information: a final compliance date, which date shall be
no later than the applicable date prescribed in Subchapter c of this Chapter;
and reasonable interim dates by which various increments of the proposed
compliance program shall be completed, such as dates when contracts will be
awarded, dates for equipment delivery and dates for construction of preliminary
structural work.
b) The Agency may adopt procedures which require data and
information in addition to and in amplification of the matters specified in
subsection (a), and which set forth the format by which all data and
information shall be submitted.