35 Ill. Adm. Code 201.510
Notice of Intent to Be Covered by a PBR (Notification)
Section
201.510Â Notice of Intent to Be Covered by a PBR (Notification)
a)Â Â Â Â Â Â Â Â An owner or operator of
a source seeking to construct or modify an emission unit pursuant to this Subpart
M and the applicable PBR Subpart must submit a complete Notification, including
fees, prior to commencing construction or modification of the emission unit. A
complete Notification containing the following information and fees must be
submitted to the Agency's Permit Section at the address provided in Section
201.530(f)(1):
1)Â Â Â Â Â Â Â Â The owner's or operator's
name, the name of the source, and the applicable Agency Bureau of Air
Identification Number;
2)Â Â Â Â Â Â Â Â Name, site address,
mailing address (if different from site address), e-mail address, and telephone
number of the source's contact;
3)Â Â Â Â Â Â Â Â Statement noting whether
the emission unit is a new emission unit or a modified emission unit (including
a reconstructed emission unit);
4)Â Â Â Â Â Â Â Â The location of the
emission unit at the source;
5)Â Â Â Â Â Â Â Â The identity of the new
emission unit or the identity of the current emission unit prior to
modification, applicable permit numbers, and the description of the
modification or reconstruction of the emission unit;
6)Â Â Â Â Â Â Â Â A statement that
indicates which PBR applies to the emission unit;
7)Â Â Â Â Â Â Â Â A statement as to
whether the proposed emission unit will be an element in a larger project; if
it is, all of the following information must also be included:
A)Â Â Â Â Â Â Â A description of the
larger project;
B)Â Â Â Â Â Â Â A statement describing
why a construction permit will not be required for any element of that project;
and
C)Â Â Â Â Â Â Â A demonstration that the potential
emissions of each regulated NSR pollutant, as defined in 40 CFR 52.21, as
incorporated by reference in Section 201.104, from the project will be less
than 80 percent of the relevant significant emission rates under 40 CFR 52.21,
35 Ill. Adm. Code 203, and any other regulations adopted pursuant to Section
9.1(c) of the Act;
8)Â Â Â Â Â Â Â Â Identification of
construction permits and PBRs received in the last two years and a
demonstration that the requested PBR should not be aggregated with, and
considered an element of, any of these projects that were addressed by the
construction permits and PBRs identified;
9)Â Â Â Â Â Â Â Â The specific information
required by the applicable PBR Subpart Notification requirement for this type
of emission unit;
10)Â Â Â Â Â Â Â Â A statement noting
whether the source is major or non-major for emissions of HAPs pursuant to
Section 39.5(2)(c)(i) of the Act. If the source is non-major, the Notification
must include documentation for the determination;
11)Â Â Â Â Â Â Â Â A certification signed
by the responsible official, as defined in Section 39.5 of the Act, that, under
penalty of law, based on information and belief formed after reasonable
inquiry, the statements and information contained in the Notification are true,
accurate, and complete and that the emission unit is eligible for the PBR
selected pursuant to subsection (a)(6); and
12)Â Â Â Â Â Â Â Â Payment of the fee that
applies to the owner or operator of the source pursuant to Section 9.12 of the
Act for the proposed construction or modification of a single emission unit.
b)Â Â Â Â Â Â Â Â
The Agency will acknowledge receipt of the Notification within 30 days.