35 Ill. Adm. Code 201.525
Standard Conditions for PBR
Section 201.525 Standard Conditions for PBR
a) Duration.
A PBR will expire one year from the date of submittal of the complete
Notification unless a continuous program of construction on this project has
commenced by that time.
b) The
construction covered by a PBR must be performed in compliance with applicable
provisions of the PBR, the Act, and regulations adopted by the Board.
c) The
owner or operator of the emission unit must comply with all applicable
requirements of Subpart M and the applicable PBR Subpart.
d) The
owner or operator of the emission unit must submit an updated Fee Determination
for CAAPP Permit form prior to commencing operation of the proposed emission
unit if there is an increase in allowable emissions over the existing permitted
allowable emissions for fee purposes as a result of the construction or
modification of the emission unit.