35 Ill. Adm. Code 201.605
Boiler Notice of Intent to Be Covered by a PBR (Notification)
Section
201.605Â Boiler Notice of Intent to Be Covered by a PBR (Notification)
The
Notification for a PBR pursuant to this Subpart must also include the following
information, in addition to the information specified by Section 201.510:
a)Â Â Â Â Â Â Â Â The primary fuel that
will be burned by the boiler, along with the maximum rated heat input capacity
of the boiler (MMBtu/hr) and a copy of the manufacturer's specifications for
the boiler.
b)Â Â Â Â Â Â Â Â Whether the boiler would
be a temporary boiler as defined by 40 CFR 60.41c and 63.7575 or 63.11237 as
incorporated by reference in Section 201.104, and, if it would be, a
demonstration that the criteria set forth in the definition of a temporary
boiler are met, and the expected period or periods in which the boiler would be
at a location or locations at the source.
c)Â Â Â Â Â Â Â Â The potential emissions
of individual pollutants from the boiler in lb/hr, tons/month, and tons/year,
including emissions of PM, PM
10
(including both filterable and
condensable particulate), PM
2.5
(including both filterable and
condensable particulate), NO
x
, CO, VOM, and SO
2
, based on
continuous operation of the boiler at its rated heat input capacity combusting
its primary fuel, with supporting documentation and calculations.
d)Â Â Â Â Â Â Â Â Whether the boiler will
have the capability to burn diesel fuel, butane, propane, or refinery fuel gas
and, if so, the potential SO
2
emissions of the boiler from the use
of such fuel.
e)Â Â Â Â Â Â Â Â If the boiler or the
source at which the boiler would be located does not meet the applicability
criteria in 35 Ill. Adm. Code 217.150(a)(1)(A) or (a)(1)(B), an identification
of the criteria that are not met, with explanation.