35 Ill. Adm. Code 215.490
Compliance Schedule (Renumbered)
Section 215
Section 215.490Â Compliance
Schedule (Renumbered)
a)Â Â Â Â Â Â Â Â The owner or operator of an emission source subject to this
Subpart, the construction or modification of which has commenced prior to (the
effective date of these amendments), must complete on-site construction,
modification or installation of the emission control and/or process equipment
or complete any necessary production process changes so as to operate in
compliance with this Subpart by April 30, 1991.
b)Â Â Â Â Â Â Â Â The owner and operator of any emission source subject to this
Subpart, the construction or modification of which has not commenced prior to
(the effective date of these amendments), shall construct such source so that
it will operate in compliance with this Subpart.