35 Ill. Adm. Code 218.762
Control Requirements
Section 218
Section 218.762Â Control
Requirements
a)Â Â Â Â Â Â Â Â Except as provided at subsection (c) of this Section, every
owner or operator of a marine terminal subject to the requirements of this
Subpart shall equip each terminal with a vapor collection and control system
that:
1)Â Â Â Â Â Â Â Â Captures the vapors displaced during the loading event and
reduces overall VOM emissions by at least 95% by weight through the use of
either a vapor combustion system or a vapor recovery system;
2)Â Â Â Â Â Â Â Â Is maintained and operated so that it prevents visible liquid
leaks, significant odors, and visible fumes in the liquid transfer and the
vapor collection lines, and appurtenances during loading; and
3)Â Â Â Â Â Â Â Â Has been certified as required by Coast Guard regulations
found at 33 CFR 154.
b)Â Â Â Â Â Â Â Â From May 1 to September 15, the regulatory control period,
every owner or operator of a marine terminal subject to the requirements of
this Subpart shall load gasoline or crude oil only into marine vessels that
are:
1)Â Â Â Â Â Â Â Â Equipped with vapor collection equipment that has been
certified as required by Coast Guard regulations found at 46 CFR 39;
2)Â Â Â Â Â Â Â Â Connected to the vapor collection system; and
3)Â Â Â Â Â Â Â Â Vapor-tight as described in the following subsections
(b)(3)(A), (b)(3)(B), (b)(3)(C), or (b)(3)(D) of this Section:
A)Â Â Â Â Â Â Â The owner or operator of the marine terminal shall load each
marine vessel with a vacuum assisted vapor collection system, instrumented in
such a way that the pump(s) transferring gasoline or crude oil to the marine
vessel will not operate unless the vapor collection system is properly
connected and properly operating.
B)Â Â Â Â Â Â Â As an alternative to subsection (b)(3)(A) of this Section, the
owner or operator of the marine terminal shall obtain documentation as
described in Section 218.770(b) of this Subpart that the marine vessel has been
vapor-tightness tested within either the preceding 12 months or the preceding
14 months, if the test is being conducted as part of the Coast Guard's
reinspection of the vessel required under 46 CFR 31.10-17, using Method 21 of
Part 60, Appendix A, incorporated by reference at Section 218.112 of this Part,
as described in Section 218.768(b) of this Subpart.
C)Â Â Â Â Â Â Â If there is no documentation of a successful leak test
conducted on the marine vessel in either the preceding 12 months or in the
preceding 14 months, if the test is being conducted as part of the Coast
Guard's reinspection of the vessel required under 46 CFR 31.10-17, the owner or
operator of the marine terminal shall require that a leak test of the marine
vessel be conducted during the final 20 percent of loading of the marine vessel
or shall not load the vessel. The test shall be conducted when the marine
vessel is being loaded at the maximum liquid transfer rate for that transfer
operation. The owner or operator of the marine terminal shall require that the
documentation described in Section 218.770(b) of this Subpart is completed
prior to the departure of the vessel.
D)Â Â Â Â Â Â Â If the marine vessel has failed its most recent vapor-tightness
leak test at the marine terminal, before the marine vessel can be loaded, the
owner or operator of the marine terminal shall require that the owner or
operator of the marine vessel provide documentation that the leaks detected
during the previous vapor-tightness leak test have been repaired and that the
marine vessel has been vapor-tightness tested since the leak(s) has been
repaired pursuant to subsection (b)(3)(B) of this Section.
c)Â Â Â Â Â Â Â Â As an alternative to the control requirements of subsections
(a) and (b) of this Section, an owner or operator of a marine terminal subject
to the control requirements of this Subpart may comply by showing:
1)Â Â Â Â Â Â Â Â Operation of a vapor collection and control system for the
loading of gasoline or crude oil from marine vessels in accordance with the
regulations adopted by the USEPA pursuant to Sections 112(d) or 183(f) of the
CAA;
2)Â Â Â Â Â Â Â Â Reduction of VOM emissions equivalent to the levels in
Appendix E of this Part through a federally enforceable emission reduction
plan; or
3)Â Â Â Â Â Â Â Â An alternate procedure to those described that has been
approved by the Agency and the USEPA in a federally enforceable permit or as a
SIP revision.
d)Â Â Â Â Â Â Â Â Nothing in this Subpart shall supersede any U.S. Coast Guard
regulation that is more stringent than that contained in this Subpart.