35 Ill. Adm. Code 225.296
Combined Pollutant Standard: Control Technology Requirements for NOx, SO2, and PM Emissions
Section
225.296 Combined Pollutant Standard: Control Technology Requirements for NO
x
,
SO
2
, and PM Emissions
a) Control Technology
Requirements for NO
x
and SO
2
.
1) On or before December
31, 2013, the owner or operator must either permanently shut down or install
and have operational FGD equipment on Waukegan 7;
2) On or before December
31, 2014, the owner or operator must either permanently shut down or install
and have operational FGD equipment on Waukegan 8;
3) On or before December
31, 2015, the owner or operator must either permanently shut down or install
and have operational FGD equipment on Fisk 19;
4) If Crawford 7 will be
operated after December 31, 2018, and not permanently shut down by this date,
the owner or operator must:
A) On or before December 31,
2015, install and have operational SNCR or equipment capable of delivering
essentially equivalent NO
x
reductions on Crawford 7; and
B) On or before December 31,
2018, install and have operational FGD equipment on Crawford 7;
5) If Crawford 8 will be
operated after December 31, 2017 and not permanently shut down by this date,
the owner or operator must:
A) On or before December 31,
2015, install and have operational SNCR or equipment capable of delivering
essentially equivalent NO
x
emissions reductions on Crawford 8; and
B) On or before December 31,
2017, install and have operational FGD equipment on Crawford 8.
b) Other Control Technology
Requirements for SO
2
. On and after April 16, 2015, Will County 3
must not combust coal. On and after December 31, 2016, Joliet 6, 7, and 8 must
not combust coal. Owners or operators of the other specified EGUs must
permanently shut down, permanently cease combusting coal at, or install FGD
equipment on each specified EGU (except Will County 4), on or before December
31, 2018, unless an earlier date is specified in subsection (a) of this
Section.
c) Control Technology
Requirements for PM. The owner or operator of the specified EGU listed in this
subsection that is equipped with a hot-side ESP must replace the hot-side ESP
with a cold-side ESP, install an appropriately designed fabric filter, or
permanently shut down the EGU by the date specified. Hot-side ESP means an ESP
on a coal-fired boiler that is installed before the boiler's air-preheater
where the operating temperature is typically at least 550ºF, as distinguished
from a cold-side ESP that is installed after the air pre-heater where the
operating temperature is typically no more than 350ºF. Waukegan 7 on or before
December 31, 2013.
d) Beginning on December
31, 2008, and annually thereafter up to and including December 31, 2015, the
owner or operator of the Fisk power plant must submit in writing to the Agency
a report on any technology or equipment designed to affect air quality that has
been considered or explored for the Fisk power plant in the preceding 12
months. This report will not obligate the owner or operator to install any
equipment described in the report.
e) Notwithstanding 35 Ill.
Adm. Code 201.146(hhh), until an EGU has complied with the applicable
requirements of subsections 225.296(a), (b), and (c), the owner or operator of
the EGU must obtain a construction permit for any new or modified air pollution
control equipment that it proposes to construct for control of emissions of
mercury, NO
x
, PM, or SO
2
.