35 Ill. Adm. Code 225.420
Permit Requirements
Section
225.420 Permit Requirements
a) Permit requirements:
1) The owner or operator of
each source with a CAIR NO
x
unit is required to submit:
A) A complete permit
application addressing all applicable CAIR NO
x
Annual Trading Program
requirements for a permit meeting the requirements of this Section, applicable
to each CAIR NO
x
unit at the source. Each CAIR permit must contain
elements required for a complete CAIR permit application pursuant to subsection
(b)(2) of this Section.
B) Any supplemental
information that the Agency determines necessary in order to review a CAIR
permit application and issue any CAIR permit.
2) Each CAIR permit will be
issued pursuant to Sections 39 and 39.5 of the Act, must contain federally
enforceable conditions addressing all applicable CAIR NO
x
Annual
Trading Program
requirements, and will be a complete and segregable
portion of the source's entire permit pursuant to subsection (a)(1) of this
Section.
3) No CAIR permit may be
issued until the Agency and USEPA have received a complete certificate of
representation for a CAIR designated representative pursuant to 40 CFR 96,
subpart BB, for the CAIR NO
x
source and the CAIR NO
x
unit
at the source.
4) For all CAIR NO
x
units that commenced operation before December 31, 2007, the owner or operator
of the unit must submit a CAIR permit application meeting the requirements of
this Section on or before December 31, 2007.
5) For all CAIR NO
x
units that commence operation on or after December 31, 2007, the owner or
operator of these units must submit applications for construction and operating
permits pursuant to the requirements of Sections 39 and 39.5 of the Act, as
applicable, and 35 Ill. Adm. Code 201 and the applications must specify that
they are applying for CAIR permits and must address the CAIR permit application
requirements of this Section.
b) Permit applications:
1) Duty to apply: The
owner or operator of any source with one or more CAIR NO
x
units must
submit to the Agency a CAIR permit application for the source covering each
CAIR NO
x
unit pursuant to subsection (b)(2) of this Section by the
applicable deadline in subsection (a)(4) or (a)(5) of this Section. The owner
or operator of any source with one or more CAIR NO
x
units must
reapply for a CAIR permit for the source as required by this Subpart, 35 Ill.
Adm. Code 201, and, as applicable, Sections 39 and 39.5 of the Act.
2) Information requirements
for CAIR permit applications: A complete CAIR permit application must include
the following elements concerning the source for which the application is
submitted:
A) Identification of the
source, including plant name. The ORIS (Office of Regulatory Information
Systems) or facility code assigned to the source by the Energy Information
Administration must also be included, if applicable;
B) Identification of each
CAIR NO
x
unit at the source; and
C) The compliance
requirements applicable to each CAIR NO
x
unit as set forth in
Section 225.410.
3) An application for a
CAIR permit will be treated as a modification of the CAIR NO
x
source's existing federally enforceable permit, if such a permit has been
issued for that source, and will be subject to the same procedural
requirements. When the Agency issues a CAIR permit pursuant to the
requirements of this Section, it will be incorporated into and become part of
that source's existing federally enforceable permit.
c) Permit content: Each
CAIR permit is deemed to incorporate automatically the definitions and terms specified
in Section 225.130 and 40 CFR 96.102, as incorporated by reference in Section
225.140 and, upon recordation of USEPA under 40 CFR 96, subparts FF and GG, as
incorporated by reference in Section 225.140, every allocation, transfer, or
deduction of a CAIR NO
x
allowance to or from the compliance account
of the CAIR NO
x
source covered by the permit.