35 Ill. Adm. Code 225.150
Commence Commercial Operation
Section 225.150 Commence
Commercial Operation
Commence
commercial operation means, for the purposes of Subparts C, D and E, with
regard to a unit:
a) To have begun to produce
steam, gas, or other heated medium used to generate electricity for sale or
use, including test generation, except as provided in 40 CFR 96.105, 96.205, or
96.305, as incorporated by reference in Section 225.140.
1) For a unit that is a CAIR
SO
2
unit, CAIR NO
x
unit, or a CAIR NO
x
Ozone
Season unit pursuant to Sections 225.305, 225.405, and 225.505, respectively,
on the date the unit commences commercial operation on the later of November
15, 1990 or the date the unit commences commercial operation as defined in
subsection (a) of this Section and that subsequently undergoes a physical
change (other than replacement of the unit by a unit at the same source), such
date will remain the unit's date of commencement of commercial operation, which
will continue to be treated as the same unit.
2) For a unit that is a CAIR
SO
2
unit, CAIR NO
x
unit, or a CAIR NO
x
Ozone
Season unit pursuant to Sections 225.305, 225.405, and 225.505, respectively,
on the later of November 15, 1990 or the date the unit commences commercial
operation as defined in subsection (a) of this Section and that is subsequently
replaced by a unit at the same source (e.g., repowered), such date will remain
the replaced unit's date of commencement of commercial operation, and the replacement
unit will be treated as a separate unit with a separate date for commencement
of commercial operation as defined in subsection (a) or (b) of this Section as
appropriate.
b) Notwithstanding
subsection (a) of this Section and except as provided in 40 CFR 96.105, 96.205,
or 96.305 for a unit that is not a CAIR SO
2
unit, CAIR NO
x
unit, or a CAIR NO
x
Ozone Season unit pursuant to Section 225.305,
225.405, or 225.505, respectively, on the later of November 15, 1990 or the
date the unit commences commercial operation as defined in subsection (a) of
this Section, the unit's date for commencement of commercial operation will be
the date on which the unit becomes a CAIR SO
2
unit, CAIR NO
x
unit, or CAIR NO
x
Ozone Season unit pursuant to Section 225.305,
225.405, or 225.505, respectively.
1) For a unit with a date
for commencement of commercial operation as defined in subsection (b) of this
Section and that subsequently undergoes a physical change (other than
replacement of the unit by a unit at the same source), such date will remain
the unit's date of commencement of commercial operation, which shall continue
to be treated as the same unit.
2) For a unit with a date
for commencement of commercial operation as defined in subsection (b) of this
Section and that is subsequently replaced by a unit at the same source (e.g.,
repowered), such date will remain the replaced unit's date of commencement of
commercial operation, and the replacement unit will be treated as a separate
unit with a separate date for commencement of commercial operation as defined
in subsection (a) or (b) of this Section as appropriate.