Applicability
Section
225.305 Applicability
a) Except as provided in
subsections (b)(1), (b)(3), and (b)(4) of this Section:
1) The following units are
CAIR SO
2
units, and any source that includes one or more such units
is a CAIR SO
2
source subject to the requirements of this Subpart C: any
stationary, fossil-fuel-fired boiler or stationary, fossil-fuel-fired
combustion turbine serving at any time, since the later of November 15, 1990 or
the start-up of the unit's combustion chamber, a generator with nameplate
capacity of more than 25 MWe producing electricity for sale.
2) If a stationary boiler
or stationary combustion turbine that, pursuant to subsection (a)(1) of this
Section, is not a CAIR SO
2
unit begins to combust fossil fuel or to
serve a generator with nameplate capacity of more than 25 MWe producing
electricity for sale, the unit will become a CAIR SO
2
unit as
provided in subsection (a)(1) of this Section on the first date on which it
both combusts fossil fuel and serves such generator.
b) The units that meet the
requirements set forth in subsections (b)(1), (b)(3), and (b)(4) of this
Section will not be CAIR SO
2
units and units that meet the
requirements of subsections (b)(2) and (b)(5) of this Section are CAIR SO
2
units:
1) Any unit that would
otherwise be classified as a CAIR SO
2
unit pursuant to subsection
(a)(1) or (a)(2) of this Section and:
A) Qualifies as a
cogeneration unit during the 12-month period starting on the date the unit
first produces electricity and continues to qualify as a cogeneration unit; and
B) Does not serve at any
time, since the later of November 15, 1990 or the start-up of the unit's
combustion chamber, a generator with nameplate capacity of more than 25 MWe
supplying any calendar year more than one-third of the unit's potential
electric output capacity or 219,000 MWh, whichever is greater, to any utility
power distribution for sale.
2) If a unit qualifies as a
cogeneration unit during the 12-month period starting on the date the unit
first produces electricity and meets the requirements of subsection (b)(1) of
this Section for at least one calendar year, but subsequently no longer meets
all such requirements, the unit shall become a CAIR SO
2
unit
starting on the earlier of January 1 after the first calendar year during which
the unit no longer qualifies as a cogeneration unit or January 1 after the
first calendar year during which the unit no longer meets the requirements of
subsection (b)(1)(B) of this Section.
3) Any unit that would
otherwise be classified as a CAIR SO
2
unit pursuant to subsection
(a)(1) or (a)(2) of this Section commencing operation before January 1, 1985
and:
A) Qualifies as a solid
waste incineration unit; and
B) Has an average annual
fuel consumption of non-fossil fuel for 1985-1987 exceeding 80 percent (on a
Btu basis) and an average annual fuel consumption of non-fossil fuel for any
three consecutive calendar years after 1990 exceeding 80 percent (on a Btu
basis).
4) Any unit that would
otherwise be classified as a CAIR SO
2
unit under subsection (a)(1)
or (a)(2) of this Section commencing operation on or after January 1, 1985 and:
A) Qualifies as a solid
waste incineration unit; and
B) Has an average annual
fuel consumption of non-fossil fuel the first three years of operation
exceeding 80 percent (on a Btu basis) and an average annual fuel consumption of
non-fossil fuel for any three consecutive calendar years after 1990 exceeding
80 percent (on a Btu basis).
5) If a unit qualifies as a
solid waste incineration unit and meets the requirements of subsection (b)(3)
or (b)(4) of this Section for at least three consecutive years, but
subsequently no longer meets all such requirements, the unit shall become a
CAIR SO
2
unit starting on the earlier of January 1 after the first
three consecutive calendar years after 1990 for which the unit has an average
annual fuel consumption of 20 percent or more.