35 Ill. Adm. Code 225.520
Permit Requirements
Section
225.520 Permit Requirements
a) Permit requirements:
1) The owner or operator of
each source with a CAIR NO
x
Ozone Season unit is required to submit:
A) A complete permit
application addressing all applicable CAIR NO
x
Ozone Season Trading Program
requirements for a permit meeting the requirements of this Section, applicable
to each CAIR NO
x
Ozone Season unit at the source. Each CAIR permit
must contain elements required for a complete CAIR permit application pursuant to
subsection (b)(2) of this Section.
B) Any supplemental
information that the Agency determines necessary in order to review a CAIR
permit application and issue any CAIR permit.
2) Each CAIR permit will be
issued pursuant to Sections 39 and 39.5 of the Act and will contain federally
enforceable conditions addressing all applicable CAIR NO
x
Ozone
Season Trading Program
requirements and will be a complete and
segregable portion of the source's entire permit pursuant to subsection (a)(1)
of this Section.
3) No CAIR permit may be
issued until the Agency and USEPA have received a complete certificate of
representation for a CAIR designated representative pursuant to 40 CFR 96,
subpart BBBB, for the CAIR NO
x
Ozone Season source and the CAIR NO
x
Ozone Season unit at the source.
4) For all CAIR NO
x
Ozone Season units that commenced operation before December 31, 2007, the owner
or operator of the unit must submit a CAIR permit application meeting the
requirements of this Section on or before December 31, 2007.
5) For all units that
commence operation on or after December 31, 2007, the owner or operator of
these units must submit applications for construction and operating permits
pursuant to the requirements of Sections 39 and 39.5 of the Act, as applicable,
and 35 Ill. Adm. Code 201, and the applications must specify that they are
applying for CAIR permits and must address the CAIR permit application
requirements of this Section 225.520.
b) Permit applications:
1) Duty to apply: The
owner or operator of any source with one or more CAIR NO
x
Ozone
Season units must submit to the Agency a CAIR permit application for the source
covering each CAIR NO
x
Ozone Season unit pursuant to subsection
(b)(2) of this Section by the applicable deadline in subsection (a)(4) or
(a)(5) of this Section. The owner or operator of any source with one or more
CAIR NO
x
Ozone Season units must reapply for a CAIR permit for the
source as required by this Subpart, 35 Ill. Adm. Code 201, and, as applicable, Sections
39 and 39.5 of the Act.
2) Information requirements
for CAIR permit applications. A complete CAIR permit application must include
the following elements concerning the source for which the application is
submitted:
A) Identification of the
source, including plant name. The ORIS (Office of Regulatory Information
Systems) or facility code assigned to the source by the Energy Information
Administration must also be included, if applicable;
B) Identification of each
CAIR NO
x
Ozone Season unit at the source; and
C) The compliance
requirements applicable to each CAIR NO
x
Ozone Season unit as set
forth in Section 225.510.
3) An application for a
CAIR permit will be treated as a modification of the CAIR NO
x
Ozone
Season source's existing federally enforceable permit, if such a permit has
been issued for that source, and will be subject to the same procedural
requirements. When the Agency issues a CAIR permit pursuant to the
requirements of this Section, it will be incorporated into and become part of
that source's existing federally enforceable permit.
c) Permit content: Each
CAIR permit is deemed to incorporate automatically the definitions and terms specified
in Section 225.130 and 40 CFR 96.302, as incorporated by reference in Section
225.140, and, upon recordation of USEPA under 40 CFR 96, subparts FFFF and GGGG,
as incorporated by reference in Section 225.140, every allocation, transfer, or
deduction of a CAIR NO
x
Ozone Season allowance to or from the
compliance account of the CAIR NO
x
Ozone Season source covered by
the permit.