35 Ill. Adm. Code 261.390
Amendments to Grant Agreement and Minor Project Scope of Work Changes
Section 261.390 Amendments to Grant Agreement and Minor
Project Scope of Work Changes
From time to time, the Agency and grant recipient may
propose changes to the grant agreement and mutually agree to changes to the
grant agreement.
a) Amendments
to the Grant Agreement. A grant amendment is a significant change to the grant
agreement that generally may include, but may not be limited to, changes to the
total project cost, number of vehicles affected, grant period, or project air
quality benefit. The grant agreement may be amended only by the mutual consent
of the parties set forth in writing as a grant amendment, signed and dated by
the Agency and the grant recipient. The following requirements and procedures
apply to grant amendments:
1) The
grant recipient may request a grant amendment at any point during the grant
period. Requests for grant amendments must be submitted in writing to the
Agency by the grant recipient's representative as defined in Section 261.360(a)
(Grant Applications) of this Subpart.
2) The
Agency shall notify the grant recipient in writing of its approval or rejection
of the requested grant amendment no more than 90 calendar days after receipt of
a request for a grant amendment.
3) Permissible
grant amendments may include, but are not limited to, the following:
A) The
original project cost approval was based on estimated costs or contractor bids
and the actual costs or contractor bids are greater or less than the estimated
costs;
B) Amendments
to State or federal statutes or regulations have affected or will affect the
project costs;
C) A project scope of work
element was inadvertently omitted; or
D) A
project scope of work element was added pursuant to applicable local, State, or
federal law.
4) A
grant amendment becomes effective when signed by both the Agency and the grant
recipient, and approved by the State. Following acceptance, the Agency shall
issue a project amendment confirmation letter, including a signed copy of the
grant amendment, to the grant recipient.
5) A
grant recipient is not eligible to obtain a grant amendment by default due to
the Agency's failure to act within the time frame set forth in this Section.
b) Minor
Project Scope of Work Changes. A minor project scope of work change includes,
but is not limited to, a change in location that does not affect air quality
benefit, a change in equipment specification such as engine displacement
capacity or equipment manufacturer, or other similar change, which is not a
grant amendment. The following requirements and procedures apply to minor
project scope of work changes:
1) Grant
recipients shall notify the Agency, in writing, of all proposed minor project
scope of work changes.
2) The
Agency may approve proposed minor project scope of work changes that it
determines are cost-effective and within the overall scope, criteria, requirements,
and limitations of the grant project.
3) The
Agency shall notify the grant recipient in writing of its approval or rejection
of the request.
4) A
grant recipient cannot obtain approval of a project scope of work change by
default due to the Agency's failure to respond to such a request.