35 Ill. Adm. Code 270.307
Agency Action on CAAPP Applications
Section 270
Section 270.307 Agency
Action on CAAPP Applications
a) In accordance with Section 39.5(10) of the Act,
the Agency
shall issue or deny the CAAPP permit within 18 months after the date of receipt
of the complete CAAPP application, with the following exceptions,
1)
Permits for affected sources for acid deposition shall be
issued or denied within 6 months after receipt of a complete application in
accordance with
Section 39.5(17) of the Act;
2)
The Agency shall act on initial CAAPP applications within
24 months after the date of receipt of the complete CAAPP application;
and
3)
The Agency shall act on complete applications containing
early reduction demonstrations under Section 112(i)(5) of the Clean Air Act
within 9 months of receipt of the complete CAAPP application.
(See Section
39.5(5)(j) of the Act)
b)
Where the Agency does not take final action on the permit
within the required time period, the permit shall not be deemed issued; rather,
the failure to act shall be treated as a final permit action for purposes of
judicial review pursuant to Sections 40.2 and 41 of
the
Act.
(See
Section 39.5(5)(j) of the Act)