35 Ill. Adm. Code 309.201
Preamble
Section 309
Section 309.201 Preamble
a) This Subpart B establishes basic rules for issuing permits to
construct, modify, and operate treatment works, pretreatment works, sewers,
wastewater sources, and other discharges that are not required to have NPDES
Permits.
b) The following discharges are exempt from the operating permit
requirement of this Subpart. However, they may be subject to the construction
permit requirement:
1) discharges for which a pretreatment permit has been issued by
the Agency under 35 Ill. Adm. Code 310;
2) discharges for which a pretreatment permit has been issued by
USEPA under the federal Clean Water Act; or
3) discharges for which an authorization has been issued by a
publicly owned treatment works (POTW) with a pretreatment program approved by
the Agency under 35 Ill. Adm. Code 310 or approved by USEPA under federal law.