35 Ill. Adm. Code 309.225
Applications – Filing and Final Action By Agency
Section 309
Section 309.225Â Applications
– Filing and Final Action By Agency
a)Â Â Â Â Â Â Â Â An application for a permit under Subpart B is not deemed to
be filed until the Agency has received, at the designated address, all
information, documents, and authorizations in the form and with the content
required by Sections 309.221, 309.222, and 309.223 and related Agency
procedures; however, if the Agency fails to notify the applicant within 30 days
after the filing of a purported application that the application is incomplete
and the reason the Agency deems it incomplete, the application must be deemed
to have been filed on the date of the purported filing. The applicant may treat
the Agency's notification that an application is incomplete as a denial of the
application for purposes of review.
b)Â Â Â Â Â Â Â Â If the Agency fails to take final action, by granting or
denying the permit as requested or with conditions, within 90 days after the
filing of the application, the applicant may deem the permit granted for a one-year
period starting on the 91st day after the application under Subpart B was
filed.
c)Â Â Â Â Â Â Â Â Any applicant for a permit under Subpart B may waive the
requirement that the Agency must take final action within 90 days after the
filing of the application.
d)Â Â Â Â Â Â Â Â The Agency must send written notice of final action taken.
e)Â Â Â Â Â Â Â Â The Agency is deemed to have taken final action on the date
that the notice is mailed.