35 Ill. Adm. Code 3650.365.340
Project Priority List
TITLE 35: ENVIRONMENTAL PROTECTION
SUBTITLE C: WATER POLLUTION
CHAPTER II: ENVIRONMENTAL PROTECTION AGENCY
PART 365 PROCEDURES FOR ISSUING LOANS FROM THE WATER POLLUTION CONTROL LOAN PROGRAM
SECTION 365.340 PROJECT PRIORITY LIST
Section 365.340
Project Priority List
a) The Agency shall
not provide financial assistance from the State Water Revolving Fund under this
Part to projects that are not on the Agency's Project Priority List.
b) The Agency shall
develop a Project Priority List for each fiscal year beginning on July 1. Only
loan applicants who have submitted a Funding Nomination Form will be placed on
the Project Priority List. Loan applicants who have received project planning
approval pursuant to Sections
365
.320 and 365.330
before March 31 of the previous fiscal year will be scored, ranked and placed
on the project priority list according to Section 365.345. Loan applicants who
have not received project planning approval before March 31 of the previous
fiscal year will be placed at the bottom of the Project Priority List in
alphabetical order.
c) The Agency shall
publish the Project Priority List in the Intended Use Plan.
d) Intended Funding
List
1) The Agency shall
identify the Intended Funding List in the Intended Use Plan. The Intended
Funding List is comprised of the highest ranking projects on the Project
Priority List that have been scored and ranked pursuant to subsection (b) and are
scheduled to initiate construction prior to March 31 of the current fiscal
year. The total costs of all projects on the intended funding list shall not
exceed the total amount of funds available.
2) Projects on the
Intended Funding List are afforded priority of resources, including, but not
limited to, preference in securing a loan as soon as the necessary programmatic
and financial steps are completed.
3) Projects on the
Intended Funding List are not guaranteed funding or additional subsidization.
4) Projects not on
the Intended Funding List may receive funding in advance of those projects
identified in the Intended Funding List according to the process set forth in
subsection (e).
e) Bypass Process
and Surplus Funding
1) From January 1
through June 30 of each year, a project on the Intended Funding List may be
bypassed, releasing any reserved funds when the loan applicant has not:
A) submitted a loan
application as required by Section 365.350(a);
B) obtained all
necessary construction permits; and
C) established a bid
opening date prior to March 31 of the current fiscal year.
2) A project on the
Intended Funding List may be bypassed at anytime, releasing any reserved funds,
when the loan applicant notifies the Agency in writing that it does not intend
to pursue funding during the current fiscal year.
3) When a project
is bypassed, the Agency will make the bypassed funds available for projects on
the Project Priority List in the order in which the requirements of Section
365.410 are satisfied by the loan applicant.
f) Surplus
funding. When the total costs of projects on the Intended Funding List is less
than the total amount of funds available, the Agency may make surplus funds
available for projects on the Project Priority List by issuing a Letter of
Commitment pursuant to Section 365.355.