35 Ill. Adm. Code 310.320
Compensation for Overflow
Section 310
Section 310.320Â Compensation
for Overflow
A POTW that overflows untreated
wastewater to receiving waters one or more times in a year may claim consistent
removal of a pollutant only by complying with subsection (a) or (b). However,
this Section will not apply if an industrial user demonstrates that overflow
does not occur between the industrial user and the POTW treatment plant.
a)Â Â Â Â Â Â Â Â The industrial user provides containment or otherwise ceases
or reduces discharges from the regulated processes that contain the pollutant
for which an allowance is requested during all circumstances in which an
overflow event can reasonably be expected to occur at the POTW or at a sewer to
which the industrial user is connected. Discharges must cease or be reduced,
or pretreatment must be increased, to the extent necessary to compensate for
the removal not being provided by the POTW. The Agency must allow allowances
under this subsection only if the POTW demonstrates the following to the
Agency:
1)Â Â Â Â Â Â Â Â That all industrial users to which the POTW proposes to apply
this subsection (a) have demonstrated the ability to contain or otherwise cease
or reduce, during circumstances in which an overflow event can reasonably be
expected to occur, discharges from the regulated processes that contain
pollutants for which an allowance is requested;
2)Â Â Â Â Â Â Â Â That the POTW has identified circumstances in which an
overflow event can reasonably be expected to occur, and has a notification or
other viable plan to ensure that industrial users will learn of an impending
overflow in sufficient time to contain, cease, or reduce discharging to prevent
untreated overflows from occurring. The POTW must also demonstrate that it
will monitor and verify the data required in subsection (a)(3) to ensure that
industrial users are containing, ceasing, or reducing operations during POTW
system overflow; and
3)Â Â Â Â Â Â Â Â That all industrial users to which the POTW proposes to apply
this subsection have demonstrated the ability and commitment to collect and
make available upon request by the POTW or the Agency daily flow reports or
other data sufficient to demonstrate that all discharges from regulated
processes containing the pollutant for which the allowance is requested were
contained, reduced, or otherwise stopped as appropriate during all
circumstances in which an overflow event was reasonably expected to occur; or
b)Â Â Â Â Â Â Â Â Reduction in Removal
1)Â Â Â Â Â Â Â Â The consistent removal claimed is reduced pursuant to the
following equation:
r
c
=
(8760 - Z)r
m
8760
where:
r
m
=
POTW's consistent removal rate
for that pollutant as established under this Subpart.
r
c
=
Removal corrected by the
overflow factor.
Z
=
Hours per year that overflow
occurred between the industrial user and the POTW treatment plant, the hours
either to be shown in the POTW's current NPDES permit application or the
hours, as demonstrated by verifiable techniques, that a particular industrial
user's discharge overflows between the industrial user and the POTW treatment
plan.
2)Â Â Â Â Â Â Â Â The industrial user can claim consistent removal only if the
POTW is complying with all NPDES permit requirements and any additional
requirements in any order or decree that affects combined sewer overflows.Â
These requirements include any combined sewer overflow requirements that
conform to the "Combined Sewer Overflow (CSO) Control Policy," USEPA
document number EPA-830/Z-94-001, incorporated by reference in Section 310.107
.
BOARD NOTE:Â Derived from 40 CFR
403.7(h) (2005), as amended at 70 Fed. Reg. 60134 (Oct. 14, 2005).