35 Ill. Adm. Code 310.350
Continuation of Authorization
Section 310
Section 310.350Â Continuation
of Authorization
a)        Inclusion in POTW Permit. Once a POTW has received
authorization to grant removal credits for a particular pollutant regulated in
a categorical pretreatment standard it may automatically extend that removal
credit to the same pollutant when it is regulated in other categorical
standards, unless granting the removal credit will cause the POTW to violate
the sludge requirements identified in Section 310.303(d) or its NPDES permit
limitations and conditions as required by Section 310.303(e). If a POTW elects
at a later time to extend removal credits to a certain categorical pretreatment
standard, industrial subcategory, or one or more industrial users that
initially were not granted removal credits, it must notify the Agency.
b)        Compliance Monitoring. Once authority is granted, the removal
credits must be included in the POTW's NPDES permit as soon as possible and must
become an enforceable requirement of the POTW's NPDES permit. The removal
credits will remain in effect for the term of the POTW's NPDES permit if the
POTW maintains compliance with the conditions specified in Section 310.351.
c)        Modification or Withdrawal of Removal Credits. Following
authorization to grant removal credits, a POTW must continue to monitor and
report the POTW's removal capabilities at intervals specified by the Agency in
the pretreatment program and NPDES permit, but in no case less than once per
year. The Agency must require a minimum of one representative sample per month
during the reporting period. The POTW must include all sampling data in the
POTW's compliance report.
BOARD NOTE:Â Derived from 40 CFR 403.7(f)(1) through (f)(3) (2003).