35 Ill. Adm. Code 310.603
Compliance Schedule
Section 310
Section 310.603 Compliance
Schedule
The following conditions apply
to the schedule required by Section 310.602(g):
a) The schedule must contain increments of progress in the form
of dates for the commencement and completion of major events leading to the
construction and operation of additional pretreatment required for the
industrial user to meet the applicable categorical pretreatment standards
(e.g., hiring an engineer, completing preliminary plans, completing final
plans, executing a contract for major components, commencing construction,
completing construction, etc.).
b) No increment referred to in subsection (a) may exceed nine months.
c) Not later than 14 days following each date in the schedule and
the final date for compliance, the industrial user must submit a progress
report to the Control Authority including, at a minimum, whether or not it
complied with the increment of progress to be met on such date and, if not, the
date on which it expects to comply with this increment of progress, the reasons
for delay, and the steps being taken by the industrial user to return the
construction to the schedule established. In no event may more than nine months
elapse between such progress reports to the Control Authority.
BOARD NOTE: Derived from 40 CFR 403.12(c) (2003).