35 Ill. Adm. Code 325.210
Proration of Fees
Section 325.210 Proration of Fees
a) Proration of New Permit
Fees
1)
In
the case of a new NPDES or sludge permit issued during the months of January
through June, the Agency may prorate the initial annual fee payable under this
Section.
[415 ILCS 5/12.5(c)] There is no proration of construction site
stormwater discharge NPDES permit fees.
2) Applicants
for new NPDES or sludge permits issued between July 1 and December 31 must pay
the entire fee due under Section 325.205.
3) Applicants
for new NPDES or sludge permits issued between January 1 and May 31 will be
charged a prorated fee according to the following schedule based on the month
in which the permit is issued.
A) January:
50 percent of the appropriate annual fee amount or $250, whichever is greater.
B) February:
40 percent of the appropriate annual fee amount or $250, whichever is greater.
C) March:
30 percent of the appropriate annual fee amount or $250, whichever is greater.
D) April:
20 percent of the appropriate annual fee amount or $250, whichever is greater.
E) May:
10 percent of the appropriate annual fee amount or $250, whichever is greater.
4) For
new NPDES or sludge permits issued in June, the applicant must pay the entire
annual fee for the following fiscal year prior to issuance of the permit.
5) The
minimum fee that may be paid pursuant to this subsection (a) is $250.
b) Proration of Fees Due Following
Permit Modifications.
If a requested modification to
an existing NPDES permit causes a change in the applicable fee categories under
Section 325.205
that results in an increase in the required fee, the
permittee must pay to the Agency the amount of the increase, prorated for the
number of months remaining
prior to
the next July 1, before the
modification is granted.
[415 ILCS 5/12.5(c)] For purposes of calculating
the prorated fee due under this subsection, partial months will be rounded down