35 Ill. Adm. Code 360.801
Determination of Allowable Costs
Section 360
Section 360.801
Determination of Allowable Costs
a) The grantee will be paid, upon request, in accordance with
General Condition Section 360.804, (Grant Payment Schedule) hereof, for the
state share of all necessary costs within the scope of the approved project not
to exceed the total grant offer and determined to be allowable in accordance
with the following criteria:
b) Allowable project costs.
Allocable project costs of the grantee which are reasonable
and necessary are allowable. Necessary costs may include, but are not limited
to:
1) Costs of salaries, benefits, and expendable material incurred
by the grantee for the project, except as provided in Section 360.801(c)(7)
below.
2) Costs under construction contracts;
3) Professional and consultant services;
4) Facility planning directly related to the treatment works;
5) Sewer system evaluation;
6) Project feasibility and engineering reports;
7) Preparation of construction drawings, specifications,
estimates, and construction contract documents;
8) Landscaping;
9) Supervision of construction work;
10) Removal and relocation or replacement of utilities for which
the grantee is legally obligated to pay;
11) Materials acquired, consumed, or expended specifically for
the project;
12) A reasonable inventory of laboratory chemicals and supplies
necessary to initiate plant operations;
13) Development and preparation of an operation and maintenance
manual; and
14) Project identification signs.
15) Flood plain insurance
c) Unallowable costs
Costs which exceed the total amount of the grant offer or are
not necessary for the construction of a treatment works project are
unallowable. Such costs include, but are not limited to:
1) Basin or areawide planning not directly related to the
project;
2) Bonus payments not legally required for completion of
construction in advance of a contractual completion date;
3) Personal injury compensation or damages arising out of the
project, whether determined by adjudication, arbitration, negotiation, or
otherwise;
4) Fines and penalties resulting from violations of, or failure
to comply with, federal, state, or local laws;
5) Costs outside the scope of the approved project;
6) Interest on bonds or any other form of indebtedness required
to finance the project costs;
7) Ordinary operating expenses of local government, such as
salaries and expenses of a mayor, city council members, or city attorney,
except as provided in Section 360.801(e) below;
8) Site acquisition (for example, sewer rights-of-way, sewage
treatment plant sites, sanitary landfills and sludge disposal areas) except as
otherwise provided in Section 360.801(d)(1) below;
9) Costs for which payment has been or will be received under
another state or federal assistance program;
10) Costs of equipment or material procured in violation of any
provisions of these General Conditions;
11) Costs of special funds (i.e., industry advancement funds;
funds to reimburse bidding costs to unsuccessful offerors, etc.) financed by
contractors, contributions in the construction industry for methods and
materials research, public and industry relations, market development,
labor-management matters, wage negotiations, jurisdictional disputes, defraying
of all or part of unsuccessful offerors bidding costs, or similar purposes;
12) Costs under construction contracts which costs are incurred
after the expiration of the applicable contractual completion date, even if the
contractual completion date is subsequently extended by the grantee, unless
such extension has been approved by the Agency in accordance with General
Condition Section 360.402, (Project Changes) hereof;
13) Personal and professional services costs (including
professional engineering costs) arising under a cost-plus-percentage of cost
type of agreement (including the multiplier contract where profit is included
in the multiplier) or a percentage-of-construction-cost type of contract;
14) Personal and professional services costs (including
professional engineering costs) when the Agency has been refused access to the
books and records of the contractor or the contractor has refused to
renegotiate a personal or professional services contract in accordance with the
provisions of General Condition Section 360.303, (Contracts for Personal and
Professional Services − Consulting Engineering Agreements) hereof; and
15) Increases in personal and professional services contract fees
which are based solely on a percentage of an increased construction cost
notwithstanding the contractual liabilities of the grantee under such contract.
d) Costs allowable, if approved.
Certain direct costs are sometimes necessary for the
construction of a treatment works and are allowable if reasonable and approved
by the Agency in the grant offer or a grant amendment. Such costs include, but
are not limited to:
1) Land acquired after October 17, 1972, that will be an integral
part of the treatment process or that will be used for ultimate disposal of
residues resulting from such treatment (for example, land for spray irrigation
of sewage effluent); and
2) Rate determination studies required pursuant to determination
of user charges under General Condition Section 360.602, (User Charges) hereof.
e) Indirect costs
Indirect costs of the grantee shall be allowable in
accordance with an indirect cost agreement negotiated and incorporated in the
grant agreement. An indirect cost agreement must identify those cost elements
allowable pursuant to Section 360.801(a) above. Where the benefits derived
from an applicant's indirect services cannot be readily determined, a lump sum
for overhead may be negotiated based upon a determination that such amount will
be approximately the same as the actual indirect costs that may be incurred.
Procedures for development of an indirect cost agreement are included as
Appendix D to these General Conditions.
f) Disputes concerning allowable costs
The grantee shall seek to resolve any questions relating to
cost allowability or allocation at its earliest opportunity (if possible, prior
to execution of the grant agreement). Final determinations by the Agency
concerning the allowability of costs shall be conclusive unless appealed within
30 days in accordance with General Condition Section 360.306, (Disputes)
hereof.
g) Limitation upon project costs incurred prior to grant award
Payment will not be authorized for costs incurred prior to
the date of the grant award except as in accordance with paragraphs (1), (2),
and (3) of this Section 360.801.
1) Step 1 or 2 projects:
A) No prior approval or prior grant award is required for Step 1
or Step 2 project work initiated on or before October 31, 1974; payment for all
such allowable costs incurred after the approved date of initiation of
construction will be authorized in conjunction with the first award of grant
assistance.
B) In the case of Step 1 or Step 2 project work initiated on or
after November 1, 1974, no payment is authorized for:
i) Step 1 costs incurred prior to the date of approval of a plan
of study by the Agency; and
ii) Step 2 costs incurred prior to the date of approval by the
Agency of a facilities plan;
iii) Payment for Step 1 or Step 2 costs incurred after such dates
of approval by the Agency will be authorized in conjunction with the first
award of grant assistance.
C) Where Step 1 or Step 2 project work is initiated after June 30,
1975, no grant for the Step 1 or Step 2 project work may be awarded unless such
award precedes initiation of the project work.
2) Step 3 projects: No grant offer for a Step 3 project will be
awarded unless such award precedes initiation of the Step 3 construction.
Advance acquisition of major equipment items requiring long lead times, or
advance construction of minor portions of treatment works, in emergencies or
instances where delay could result in significant cost increases, may be
approved by the Agency, but only:
A) If the grantee submits a written and adequately substantiated
request for approval; and
B) If written approval by the Agency is obtained prior to the initiation
of the advance acquisition or advance construction.
3) The approval of a plan of study, a facilities plan, or of
advance acquisition of equipment or advance construction will not constitute a
commitment for approval of grant assistance for a subsequent treatment works
project, but will allow payment for the previously approved costs as allowable
project costs only upon subsequent award of grant assistance, if requested
prior to grant award. In instances where such approval is obtained, the applicant
proceeds at its own risk, since payment for such costs will not be made until
grant assistance for the project is awarded.
h) Sewage collection systems.
1) No project costs will be allowed for the construction of any
sewage collection system until the Agency has made a determination in writing
prior to initiation of construction that:
A) There is a waste treatment works of sufficient existing or
planned capacity to adequately treat the sewage collected by the proposed
sewage collection system; and
B) That such project work is either for a new sewage collection
system in a previously unsewered community and that the community was in
existence on October 18, 1972, or is for replacement or major rehabilitation of
an existing sewage collection system and such replacement or rehabilitation has
been determined by the Agency to be necessary in accordance with the provisions
of General Condition Section 360.202, (Sewer System Evaluation and
Rehabilitation) hereof.
2) No project costs will be allowed for the replacement or major
rehabilitation of an existing sewage collection system if the sewage collection
system average dry weather flow design capacity exceeds 150 percent of the
average dry weather flow design capacity of the sewage collection system
existing on October 18, 1972.
3) Project costs allowable for the construction of new sewage
collection systems are limited to the design and construction of a system with
flow design capacity through the system equal to 150 percent of the waste
waters originating from the community as it existed on October 18, 1972.