35 Ill. Adm. Code 360.APPENDIX A
A General Conditions of Construction Contract Document (Document No. 11 of the Contract Documents for Construction of Federally Assisted Water and Sewer Projects)
Section 360.APPENDIX A General
Conditions of Construction Contract Document (Document No. 11 of the Contract
Documents for Construction of Federally Assisted Water and Sewer Projects)
1. Definitions
2. Additional Instructions and Detail Drawings
3. Schedules, Reports and Records
4. Drawings and Specifications
5. Shop Drawings
6. Materials, Services and Facilities
7. Inspection and Testing
8. Substitutions
9. Patents
10. Surveys, Permits, Regulations
11. Protection of Work, Property, Persons
12. Supervision by Contractor
13. Changes in Work
14. Changes in Contract Price
15. Time for Completion and Liquidated Damages
16. Correction of Work
17. Subsurface Conditions
18. Suspension of Work, Termination and Delay
19. Payments to Contractor
20. Acceptance of Final Payment as Release
21. Insurance
22. Contract Security
23. Assignments
24. Indemnification
25. Separate Contracts
26. Subcontracting
27. Engineer's Authority
28. Land and Rights-of-Way
29. Guaranty
30. Arbitration
31. Taxes
1. DEFINITIONS
1.1 Wherever used in the CONTRACT DOCUMENTS, the following terms
shall have the meanings indicated which shall be applicable to both the
singular and plural thereof:
1.2 ADDENDA − Written or graphic instruments issued prior to
the execution of the Agreement which modify or interpret the CONTRACT,
DOCUMENTS, DRAWINGS and SPECIFICATIONS, by additions, deletions, clarifications
or corrections.
1.3 BID − The offer or proposal of the BIDDER submitted on
the prescribed form setting forth the prices for the WORK to be performed.
1.4 BIDDER − Any person, firm or corporation submitting a
BID for the WORK.
1.5 BONDS − Bid, Performance, and Payment Bonds and other
instruments of security, furnished by the CONTRACTOR and his surety in
accordance with the CONTRACT DOCUMENTS.
1.6 CHANGE ORDER − A written order to the CONTRACTOR
authorizing an addition, deletion or revision in the WORK within the general
scope of the CONTRACT DOCUMENTS, or authorizing an adjustment in the CONTRACT
PRICE or CONTRACT TIME.
1.7 CONTRACT DOCUMENTS − The contract, including
Advertisement For Bids, Information For Bidders, BID, Bid Bond, Agreement,
Payment Bond, Performance Bond. NOTICE OF AWARD, NOTICE TO PROCEED, CHANGE
ORDER, DRAWINGS, SPECIFICATIONS, and ADDENDA.
1.8 CONTRACT PRICE − The total monies payable to the
CONTRACTOR under the terms and conditions of the CONTRACT DOCUMENTS.
1.9 CONTRACT TIME − The number of calendar days stated in
the CONTRACT DOCUMENTS for the completion of the WORK.
1.10 CONTRACTOR − The person, firm or corporation with whom
the OWNER has executed the Agreement.
1.11 DRAWINGS − The part of the CONTRACT DOCUMENTS which
show the characteristics and scope of the WORK to be performed and which have
been prepared by or approved by the Engineer.
1.12 ENGINEER − The person, firm or corporation named as
such in the CONTRACT DOCUMENTS.
1.13 FIELD ORDER − A written order effecting a change in the
WORK not involving an adjustment in the CONTRACT PRICE or an extension of the
CONTRACT TIME, issued by the ENGINEER to the CONTRACTOR during construction.
1.14 NOTICE OF AWARD − The written notice of the acceptance
of the BID from the OWNER to the successful BIDDER.
1.15 NOTICE TO PROCEED − Written communication issued by the
OWNER to the CONTRACTOR authorizing him to proceed with the WORK and
establishing the date of commencement of the WORK.
1.16 OWNER − A public or quasi-public body in authority,
corporation, association, partnership, or individual for whom the WORK is to be
performed.
1.17 PROJECT − The undertaking to be performed as provided
in the CONTRACT DOCUMENTS.
1.18 RESIDENT PROJECT REPRESENTATIVE − The authorized
representative of the OWNER who is assigned to the PROJECT site or any part
thereof.
1.19 SHOP DRAWINGS − All drawings, diagrams, illustrations,
brochures, schedules and other data which are prepared by the CONTRACTOR, a
SUBCONTRACTOR, manufacturer, SUPPLIER or distributor, which illustrate how
specific portions of the WORK shall be fabricated or installed.
1.20 SPECIFICATIONS − A part of the CONTRACT DOCUMENTS
consisting of written descriptions of a technical nature of materials, equipment,
construction systems, standards and workmanship.
1.21 SUBCONTRACTOR − An individual, firm or corporation
having a direct contract with the CONTRACTOR or with any other SUBCONTRACTOR by
the performance of a part of the WORK at the site.
1.22 SUBSTANTIAL COMPLETION − That date as certified by the
ENGINEER when the construction of the PROJECT or a specified part thereof is
sufficiently completed, in accordance with the CONTRACT DOCUMENTS, so that the
PROJECT or specified part can be utilized for the purposes for which it is
intended.
1.23 SUPPLEMENTAL GENERAL CONDITIONS − Modifications to
General Conditions required by a Federal agency for participation in the
PROJECT and approved by the agency in writing prior to inclusion in the
CONTRACT DOCUMENTS, or such requirements that may be imposed by applicable
state laws.
1.24 SUPPLIER − Any person or organization who supplies
materials or equipment for the WORK, including that fabricated to a special
design, but who does not perform labor at the site.
1.25 WORK − All labor necessary to produce the construction
required by the CONTRACT DOCUMENTS, and all materials and equipment
incorporated or to be incorporated in the PROJECT.
1.26 WRITTEN NOTICE − Any notice to the party of the
Agreement relative to any part of this Agreement in writing and considered
delivered and the service thereof completed, when posted by certified or
registered mail to the said party at his last given address, or delivered in
person to said party or his authorized representative on the WORK.
2. ADDITIONAL INSTRUCTIONS AND DETAIL DRAWINGS
2.1 The CONTRACTOR may be furnished additional instructions and
detail drawings, by the ENGINEER, as necessary to carry out the WORK required
by the CONTRACT DOCUMENTS.
2.2 The additional drawings and instruction thus supplied will
become a part of the CONTRACT DOCUMENTS. The CONTRACTOR shall carry out the
WORK in accordance with the additional detail drawings and instructions.
3. SCHEDULES, REPORTS AND RECORDS
3.1 The CONTRACTOR shall submit to the OWNER such schedule of
quantities and costs, progress schedules, payrolls, reports, estimates, records
and other data where applicable as are required by the CONTRACT DOCUMENTS for
the WORK to be performed.
3.2 Prior to the first partial payment estimate the CONTRACTOR
shall submit construction progress schedules showing the order in which he
proposes to carry on the WORK, including dates at which he will start the
various parts of the WORK, estimated date of completion of each part and, as
applicable:
3.2.1 The dates at which special detail drawings will be required; and
3.2.2 Respective dates for submission of SHOP DRAWINGS, the beginning
of manufacture, the testing and the installation of materials, supplies and equipment.
3.3 The CONTRACTOR shall also submit a schedule of payments that
he anticipates he will earn during the course of the WORK.
4. DRAWINGS AND SPECIFICATIONS
4.1 The intent of the DRAWINGS and SPECIFICATIONS is that the
CONTRACTOR shall furnish all labor, materials, tools, equipment, and
transportation necessary for the proper execution of the WORK in accordance
with the CONTRACT DOCUMENTS and all incidental work necessary to complete the
PROJECT in an acceptable manner, ready for use, occupancy or operation by the
OWNER.
4.2 In case of conflict between the DRAWINGS and SPECIFICATIONS,
the SPECIFICATIONS shall govern. Figure dimensions on DRAWINGS shall govern over
scale dimensions, and detailed DRAWINGS shall govern over general DRAWINGS.
4.3 Any discrepancies found between the DRAWINGS and
SPECIFICATIONS and site conditions or any inconsistencies or ambiguities in the
DRAWINGS or SPECIFICATIONS shall be immediately reported to the ENGINEER, in
writing, who shall promptly correct such inconsistencies or ambiguities in
writing. WORK done by the CONTRACTOR after his discovery of such discrepancies,
inconsistencies or ambiguities shall be done at the CONTRACTOR'S risk.
5. SHOP DRAWINGS
5.1 The CONTRACTOR shall provide SHOP DRAWINGS as may be
necessary for the prosecution of the WORK as required by the CONTRACT
DOCUMENTS. The ENGINEER shall promptly review all SHOP DRAWINGS. The
ENGINEER'S approval of any SHOP DRAWINGS shall not release the CONTRACTOR from
responsibility for deviations from the CONTRACT DOCUMENTS. The approval of any
SHOP DRAWING which substantially deviates from CONTRACT DOCUMENTS shall be
evidenced by a CHANGE ORDER.
5.2 When submitting for the ENGINEER'S review SHOP DRAWINGS
shall bear the CONTRACTOR'S certification that he has reviewed, checked and
approved the SHOP DRAWINGS and that they are in conformance with the
requirements of the CONTRACT DOCUMENTS.
5.3 Portions of the WORK requiring a SHOP DRAWING or sample
submission shall not begin until the SHOP DRAWING or submission has been
approved by the ENGINEER. A copy of each approved SHOP DRAWING and each
approved sample shall be kept in good order by the CONTRACTOR at the site and
shall be available to the ENGINEER.
6. MATERIALS, SERVICES AND FACILITIES
6.1 It is understood that except as otherwise specifically
stated in the CONTRACT DOCUMENTS, the CONTRACTOR shall provide and pay for all
materials, labor, tools, equipment, water, light, power, transportation,
supervision, temporary construction of any nature whatsoever necessary to
execute, complete, and deliver the WORK within the specified time.
6.2 Materials and equipment shall be so stored as to insure the
preservation of their quality and fitness for the WORK. Stored materials and
equipment to be incorporated in the WORK shall be located so as to facilitate
prompt inspection.
6.3 Manufactured articles, materials and equipment shall be
applied, installed, connected, erected, used, cleaned and conditioned as
directed by the manufacturer.
6.4 Materials, supplies and equipment shall be in accordance
with samples submitted by the CONTRACTOR and approved by the ENGINEER.
6.5 Materials, supplies or equipment to be incorporated into the
WORK shall not be purchased by the CONTRACTOR or the SUBCONTRACTOR subject to a
chattel mortgage or under a conditional sale contract or other agreement by
which an interest is retained by the seller.
7. INSPECTION AND TESTING
7.1 All materials and equipment used in the construction of the
PROJECT shall be subject to adequate inspection and testing in accordance with
generally accepted standards, as required and defined in the CONTRACT
DOCUMENTS.
7.2 The OWNER shall provide all inspection and testing services
not required by the CONTRACT DOCUMENTS.
7.3 The CONTRACTOR shall provide at his expense the testing and
inspection services required by the CONTRACT DOCUMENTS.
7.4 If the CONTRACT DOCUMENTS, laws, ordinances, rules,
regulations or orders of any public authority having jurisdiction require any
WORK to specifically be inspected, tested, or approved by someone other than
the CONTRACTOR, the CONTRACTOR will give the ENGINEER timely notice of
readiness. The CONTRACTOR will then furnish the ENGINEER the required
certificates of inspection, testing or approval.
7.5 Inspections, tests or approvals by the engineers or others
shall not relieve the CONTRACTOR from his obligations to perform the WORK in
accordance with the requirements of the CONTRACT DOCUMENTS.
7.6 The ENGINEER and his representatives will at all times have
access to the WORK. In addition, authorized representatives and agents of any
participating Federal or state agency shall be permitted to inspect all work,
materials, payrolls, records of personnel, invoices of materials, and other
relevant data and records. The CONTRACTOR will provide proper facilities for
such access and observation of the WORK and also for any inspection, or testing
thereof.
7.7 If any WORK is covered contrary to the written instructions
of the ENGINEER it must, if requested by the ENGINEER, be uncovered for his
observation and replaced at the CONTRACTOR'S expense.
7.8 If the ENGINEER considers it necessary or advisable that
covered WORK be inspected or tested by others, the CONTRACTOR, at the
ENGINEER'S request, will uncover, expose or otherwise make available for
observation, inspection or testing as the ENGINEER may require, that portion of
the WORK in question, furnishing all necessary labor, materials, tools, and
equipment. If it is found that such WORK is defective, the CONTRACTOR will
bear all the expenses of such uncovering, exposure, observation, inspection and
testing and of satisfactory reconstruction. If, however, such WORK is not
found to be defective, the CONTRACTOR will be allowed an increase in the
CONTRACT PRICE or an extension of the CONTRACT TIME, or both, directly
attributable to such uncovering, exposure, observation, inspection, testing and
reconstruction and an appropriate CHANGE ORDER shall be issued.
8. SUBSTITUTIONS
8.1 Whenever a material, article or piece of equipment is
identified on the DRAWINGS or SPECIFICATIONS by reference to brand name or
catalogue number, it shall be understood that this is referenced for the
purpose of defining the performance or other salient requirements and that
other products of equal capacities, quality and function shall be considered.
The CONTRACTOR may recommend the substitution of a material, article, or piece
of equipment of equal substance and function for those referred to in the
CONTRACT DOCUMENTS by reference to brand name or catalogue number, and if, in
the opinion of the ENGINEER, such material, article, or piece of equipment is
of equal substance and function to that specified, the ENGINEER may approve its
substitution and use by the CONTRACTOR. Any cost differential shall be
deductible from the CONTRACT PRICE and the CONTRACT DOCUMENTS shall be
appropriately modified by CHANGE ORDER. The CONTRACTOR warrants that if
substitutes are approved, no major changes in the function or general design of
the PROJECT will result. Incidental changes or extra component parts required
to accommodate the substitute will be made by the CONTRACTOR without a change
in the CONTRACT PRICE or CONTRACT TIME.
9. PATENTS
9.1 The CONTRACTOR shall pay all applicable royalties and
license fees. He shall defend all suits of claims for infringement of any
patent rights and save the OWNER harmless from loss on account thereof, except
that the OWNER shall be responsible for any such loss when a particular process
design on the product of a particular manufacturer or manufacturer is
specified, however, if the CONTRACTOR has reason to believe that the design
process or product specified is an infringement of a patent, he shall be responsible
for such loss unless he promptly gives such information to the ENGINEER.
10. SURVEYS, PERMITS, REGULATIONS
10.1 The OWNER shall furnish all boundary surveys and establish
all base lines for locating the principal component parts of the WORK together
with a suitable number of bench marks adjacent to the WORK as shown in the
CONTRACT DOCUMENTS. From the information provided by the OWNER, unless
otherwise specified in the CONTRACT DOCUMENTS, the CONTRACTOR shall develop and
make all detail survey, needed for construction such as slope stakes,
batterboards, stakes for pile locations and other working points, lines,
elevations and cut sheets.
10.2 The CONTRACTOR shall carefully preserve bench marks,
reference points and stakes and in case of willful or careless destruction, he
shall be charged with the resulting expense and shall be responsible for any
mistakes that may be caused by their unnecessary loss or disturbance.
10.3 Permits and licenses of a temporary nature necessary for the
prosecution of the WORK shall be secured and paid for by the CONTRACTOR unless
otherwise stated in the SUPPLEMENTAL GENERAL CONDITIONS. Permits, licenses and
easements for permanent structures or permanent changes in existing facilities
shall be secured and paid for by the OWNER, unless otherwise specified. The
CONTRACTOR shall give all notices and comply with all laws, ordinances, rules
and regulations bearing on the conduct of the WORK as drawn an specified. If
the CONTRACTOR observes that the CONTRACT DOCUMENTS are at variance therewith,
he shall promptly notify the ENGINEER in writing, and any necessary changes
shall be adjusted as provided in Section 13, CHANGES IN THE WORK.
11. PROTECTION OF WORK, PROPERTY AND PERSONS
11.1 The CONTRACTOR will be responsible for initiating,
maintaining and supervising all safety precautions and programs in connection
with the WORK. He will take all necessary precautions for the safety of and
will provide the necessary protection to prevent damage, injury affected thereby,
all the WORK and all materials or equipment to be incorporated therein, whether
in storage on or off the site, and other property at the site or adjacent
thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures
and utilities not designated for removal, relocation or replacement in the
course of construction.
11.2 The CONTRACTOR will comply with all applicable laws,
ordinances, rules, regulations and orders of any public body having
jurisdiction. He will erect and maintain, as required by the conditions and
progress of the WORK, all necessary safeguards for safety and protection. He
will notify owners of adjacent utilities when prosecution of the WORK may
affect them. The CONTRACTOR will remedy all damage, injury or loss to any
property caused directly or indirectly, in whole or in part, by the CONTRACTOR,
any SUBCONTRACTOR or anyone directly or indirectly employed by any of them or
anyone for whose acts any of them be liable, except damage or loss attributable
to the fault of the CONTRACT DOCUMENTS or to the acts or omissions of the OWNER
or the ENGINEER or anyone employed by either of them or anyone for whose acts
either of them may be liable and not attributable, directly or indirectly, in
whole or in part, to the fault or negligence of the CONTRACTOR.
11.3 In emergencies affecting the safety of persons or the WORK or
property at the site or adjacent thereto, the CONTRACTOR, without special
instruction or authorization from the ENGINEER or OWNER, shall act to prevent
threatened damage, injury or loss. He will give the ENGINEER prompt WRITTEN
NOTICE of any significant changes in the WORK or deviations from the CONTRACT
DOCUMENTS caused thereby, and a CHANGE ORDER shall thereupon be issued covering
the changes and deviations involved.
12. SUPERVISION BY CONTRACTOR
12.1 The CONTRACTOR will supervise and direct the WORK. He will
be solely responsible for the means, methods, techniques, sequences and
procedures of construction. The CONTRACTOR will employ and maintain on the
WORK a qualified supervisor or superintendent who shall have been designated in
writing by the CONTRACTOR as the CONTRACTOR'S representative at the site. The
supervisor shall have full authority to act on behalf of the CONTRACTOR and all
communications given to the supervisor shall be binding as if given to the
CONTRACTOR. The supervisor shall be present on the site at all times as
required to perform adequate supervision and coordination of the WORK.
13. CHANGES IN THE WORK
13.1 The OWNER may at any time, as the need arises, order changes
within the scope of the WORK without invalidating the Agreement. If such
changes increase or decrease the amount due under the CONTRACT DOCUMENTS or in
the time required for performance of the WORK an equitable adjustment shall be
authorized by CHANGE ORDER.
13.2 The ENGINEER, also, may at any time, by issuing a FIELD
ORDER, make changes in the details of the WORK. The CONTRACTOR shall proceed
with the performance of any changes in the WORK so ordered by the ENGINEER
unless the CONTRACTOR believes that such FIELD ORDER entitles him th a change
in CONTRACT PRICE or TIME, or both, in which event he shall give the ENGINEER
WRITTEN NOTICE thereof within seven (7) days after the receipt of the ordered
change. Thereafter the CONTRACTOR shall document the basis for the change in
CONTRACT PRICE or TIME within thirty (30) days. The CONTRACTOR shall not
execute such changes pending the receipt of an executed CHANGE ORDER or further
instruction from the OWNER.
14. CHANGES IN CONTRACT PRICE
14.1 The CONTRACT PRICE may be changed only by a CHANGE ORDER. The
value of any WORK covered by a CHANGE ORDER or of any claim for increase or
decrease in the CONTRACT PRICE shall be determined by one or more of the
following methods in the order of precedence listed below:
a. Unit prices previously approved
b. An agreed lump sum
c. The actual cost for labor, direct overhead, materials,
supplies, equipment, and other services necessary to complete the work. In
addition, there shall be added an amount to be agreed upon but not to exceed
fifteen (15) percent of the actual cost of the WORK to cover the cost of
general overhead profit.
15. TIME FOR COMPLETION AND LIQUIDATED DAMAGES
15.1 The date of beginning and the time for completion of the WORK
are essential conditions of the CONTRACT DOCUMENTS and the WORK embraced shall
be commenced on a date specified in the NOTICE TO PROCEED.
15.2 The CONTRACTOR will proceed with the WORK at such rate of
progress to insure full completion within the CONTRACT TIME. It is expressly
understood and agreed, by and between the CONTRACTOR and the OWNER, that the
CONTRACT TIME, for the completion of the WORK described herein is a reasonable
time, taking into consideration the average climatic and economic conditions
and other factors prevailing in the locality of the WORK.
15.3 If the CONTRACTOR shall fail to complete the WORK within the
CONTRACT TIME, an extension of time granted by the OWNER, then the CONTRACTOR
will pay to the OWNER the amount for liquidated damages as specified in the BID
for each calendar day that the CONTRACTOR shall be in default after the time
stipulated in the CONTRACT DOCUMENTS.
15.4 The CONTRACTOR shall not be charged with liquidated damages of
any excess cost when the delay in completion of the WORK is due to the
following and the CONTRACTOR has promptly given WRITTEN NOTICE of such delay to
the OWNER OR ENGINEER.
15.4.1 To any preference, priority or allocation order duly issued
by the OWNER
15.4.2 To unforeseeable causes beyond the control and without the
fault or negligence of the CONTRACTOR, including but not restricted to acts of
God, or of the public enemy, acts of the OWNER, acts of another CONTRACTOR in
the performance of a contract with the OWNER, fires, floods, epidemics,
quarantine restrictions, strikes, freight embargoes, and abnormal and
unforeseeable weather; and
15.4.3 To any delays of SUBCONTRACTORS occasioned by any of the
causes specified in paragraphs 15.4.1 and 15.4.2 of this article.
16. CORRECTION OF WORK
16.1 The CONTRACTOR shall promptly remove from the premises all
WORK rejected by the ENGINEER for failure to comply with the CONTRACT
DOCUMENTS, whether incorporated in the construction or not, and the CONTRACTOR
shall promptly replace and reexecute the WORK in accordance with the CONTRACT
DOCUMENTS and without expense to the OWNER and shall bear the expense of making
good all WORK of other CONTRACTORS destroyed or damaged by such removal or
replacement.
16.2 All removal and replacement WORK shall be done at the
CONTRACTOR'S expense. If the CONTRACTOR does not take action to remove such
rejected WORK within ten (10) days after receipt of WRITTEN NOTICE, the OWNER
may remove such WORK and store the materials at the expense of the CONTRACTOR.
17. SUBSURFACE CONDITIONS
17.1 The CONTRACTOR shall promptly, and before such conditions are
disturbed, except in the event of an emergency, notify the OWNER by WRITTEN
NOTICE of:
17.1.1 Subsurface or latent physical condition at the site differing
materially from those indicated in the CONTRACT DOCUMENTS; or
17.1.2 Unknown physical conditions at the site, of an unusual
nature, differing materially from those ordinarily encountered and generally
recognized as inherent in WORK of the character provided for in the CONTRACT
DOCUMENTS.
17.2 The OWNER shall promptly investigate the conditions, and if
he finds that such conditions do so materially differ and cause an increase or
decrease in the cost of, or in the time required for, performance of the WORK,
an equitable adjustment shall be made and the CONTRACT DOCUMENTS shall be
modified by a CHANGE ORDER. Any claim of the CONTRACTOR for adjustment
hereunder shall not be allowed unless he has given the required WRITTEN NOTICE,
provided that the OWNER may, if he determines the facts so justify, consider
and adjust any such claims asserted before the date of final payment.
18. SUSPENSION OF WORK, TERMINATION AND DELAY
18.1 The OWNER may suspend the WORK on any portion thereof for a
period of not more than ninety days or such further time as agreed upon by the
CONTRACTOR, by WRITTEN NOTICE to the CONTRACTOR and the ENGINEER which notice
shall fix the date on which WORK shall be resumed. The CONTRACTOR will resume
the WORK on the date so fixed. The CONTRACTOR will be allowed an increase in
the CONTRACT PRICE or an extension of the CONTRACT TIME, or both, directly
attributable to any suspension.
18.2 If the CONTRACTOR is adjudged a bankrupt or insolvent, or if
he makes a general assignment for the benefit of his creditors, or if a trustee
or receiver is appointed for the CONTRACTOR or for any of his property, of if
he files a petition to take advantage of any debtor's act, or to reorganize
under the bankruptcy or applicable laws, or if he repeatedly fails to supply
sufficient skilled workmen or suitable materials or equipment, or if he
repeatedly fails to make prompt payments to SUBCONTRACTORS or for labor,
materials or equipment or if he disregards laws, ordinances, rules, regulations
or orders of any public body having jurisdiction of the WORK or if he
disregards the authority of the ENGINEER, or if he otherwise violates any
provision of the CONTRACT DOCUMENTS, then the OWNER may, without prejudice to
any other right or remedy and after giving the CONTRACTOR and his surety a
minimum of ten (10) days from delivery of a WRITTEN NOTICE, terminate the
services of the CONTRACTOR and take possession of the PROJECT and of all
materials, equipment, tools, construction equipment and machinery thereon owned
by the CONTRACTOR, and finish the WORK by whatever method he may deem
expedient. In such case the CONTRACTOR shall not be entitled to receive any
further payment until the WORK is finished. If the unpaid balance of the
CONTRACT PRICE exceeds the direct and indirect costs of completing the PROJECT,
including compensation for additional professional services, such excess SHALL
BE PAID TO THE CONTRACTOR. If such costs exceed such unpaid balance, the
CONTRACTOR will pay the difference to the OWNER. Such costs incurred by the
OWNER will be determined by the ENGINEER and incorporated in a CHANGE ORDER.
18.3 Where the CONTRACTOR'S services have been so terminated by
the OWNER, said termination shall not affect any rights of the OWNER against
the CONTRACTOR then existing or which may thereafter accrue. Any retention or
payment of monies by the OWNER due the CONTRACTOR will not release the
CONTRACTOR from compliance with the CONTRACT DOCUMENTS.
18.4 After ten (10) days from delivery of a WRITTEN NOTICE to the
CONTRACTOR and the ENGINEER the OWNER may, without cause and without prejudice
to any other right or remedy elect to abandon the PROJECT and terminate the
CONTRACT in such case, the CONTRACTOR shall be paid for all WORK executed and
any expense sustained plus reasonable profit.
18.5 If, through no act or fault of the CONTRACTOR, the WORK is
suspended for a period of more than ninety (90) days by the OWNER or under an
order of court or other public authority or the ENGINEER fails to act on any
request for payment within thirty (30) days after it is submitted the OWNER
fails to pay the CONTRACTOR substantially the sum approved by the ENGINEER or
awarded by arbitrators within thirty (30) days of its approval and
presentation, then the CONTRACTOR may after ten (10) days from delivery of a
WRITTEN NOTICE to the OWNER and the ENGINEER, terminate the CONTRACT and
recover from the OWNER payment for all WORK executed and all expenses
sustained. In addition and in lieu of terminating the CONTRACT, if the
ENGINEER has failed to act on a request for payment or if the OWNER has failed
to make any payment as aforesaid, the CONTRACTOR may upon ten (10) days written
notice to the OWNER and the ENGINEER stop the WORK until he has been paid all
amounts then due in which event and upon resumption of the WORK, CHANGE ORDERS
shall be issued for adjusting the CONTRACT PRICE or extending the CONTRACT TIME
or both to compensate for the costs and delays attributable to the stoppage of
the WORK.
18.6 If the performance of all or any portion of the WORK is
suspended, delayed, or interrupted as a result of a failure of the OWNER or
ENGINEER to act within the time specified in the CONTRACT DOCUMENTS, or if no
time is specified, within a reasonable time, an adjustment in the CONTRACT
PRICE or an extension of the CONTRACT TIME, or both, shall be made by CHANGE
ORDER to compensate the CONTRACTOR for the costs and delays necessarily caused
by the failure of the OWNER or ENGINEER.
19. PAYMENTS TO CONTRACTOR
19.1 At least ten (10) days before each progress payment falls due
(but not more often than once a month), the CONTRACTOR will submit to the
ENGINEER a partial payment estimate filled out and signed by the CONTRACTOR
covering the WORK performed during the period covered by the partial payment
estimate and supported by such data as the ENGINEER may reasonably require. If
payment is requested on the basis of materials and equipment not incorporated
in the WORK but delivered and suitably stored at or near the site, the partial
payment estimate shall also be accompanied by such supporting data,
satisfactory to the OWNER, as will establish the OWNER'S title to the material
and equipment and protect his interest therein, including applicable insurance.
The ENGINEER will, within ten (10) days after receipt of each partial payment
estimate, either indicate in writing his approval of payment and present the
partial payment estimate to the OWNER, or return the partial payment estimate to
the CONTRACTOR indicating in writing his reasons for refusing the approve
payment. In the latter case, the CONTRACTOR may make the necessary corrections
and resubmit the partial payment estimate. The OWNER will, within ten (10) days
of presentation to him of an approved partial payment estimate, pay the
CONTRACTOR a progress payment on the basis of the approved partial payment
estimate. The OWNER shall retain ten (10) percent of the amount of each payment
until final completion and acceptance of all work covered by the CONTRACT
DOCUMENTS. The OWNER at any time, however, after fifty (50) percent of the
WORK has been completed, if he finds that satisfactory progress is being made,
shall reduce retainage to five (5%) percent on the current and remaining estimates.
When the WORK is substantially complete (operational or beneficial occupancy),
the retained amount may be further reduced below five (5) percent to only that
amount necessary to assure completion. On completion and acceptance of a part
of the WORK on which the price is stated separately in the CONTRACT DOCUMENTS,
payment may be made in full, including retained percentages, less authorized
deductions.
19.2 The request for payment may also include an allowance for the
cost of such major materials and equipment which are suitably stored either at
or near the site.
19.3 Prior to SUBSTANTIAL COMPLETION, the OWNER, with the approval
of the ENGINEER and with the concurrence of the CONTRACTOR, may use any
completed or substantially completed portions of the WORK. Such use shall not
constitute an acceptance of such portions of the WORK.
19.4 The OWNER shall have the right to enter the premises for the
purpose of doing work not covered by the CONTRACT DOCUMENTS. This provision
shall not be construed as relieving the CONTRACTOR of the sole responsibility
for the care and protection of the WORK, or the restoration of any damaged WORK
except such as may be caused by agents or employees of the OWNER.
19.5 Upon completion and acceptance of the WORK, the ENGINEER
shall issue a certificate attached to the final payment request that the WORK
has been accepted by him under the conditions of the CONTRACT DOCUMENTS. The
entire balance found to be due the CONTRACTOR, including the retained
percentages, but except such sums as may be lawfully retained by the OWNER,
shall be paid to the CONTRACTOR within thirty (30) days of completion and
acceptance of the WORK.
19.6 The CONTRACTOR will indemnify and save the OWNER or the
OWNER'S agents harmless from all claims growing out of the lawful demands of
SUBCONTRACTORS, laborers, workmen, mechanics, materialmen, and furnishers of
machinery and parts thereof, equipment, tools, and all supplies incurred in the
furtherance of the performance of the WORK. The CONTRACTOR shall, at the
OWNER'S request, furnish satisfactory evidence that all obligations of the
nature designated above have been paid, discharged, or waived. If the
CONTRACTOR fails to do so the OWNER may, after having notified the CONTRACTOR,
either pay unpaid bills or withhold from the CONTRACTOR'S unpaid compensation a
sum of money deemed reasonably sufficient to pay any and all such lawful claims
until satisfactory evidence is furnished that all liabilities have been fully
discharged whereupon payment to the CONTRACTOR shall be resumed, in accordance
with the terms of the CONTRACT DOCUMENTS, but in no event shall the provisions
of this sentence be construed to impose any obligations upon the OWNER to
either the CONTRACTOR, his Surety, or any third party. In paying any unpaid
bills of the CONTRACTOR, any payment so made by the OWNER shall be considered
as a payment made under the CONTRACT DOCUMENTS by the OWNER to the CONTRACTOR
and the OWNER shall not be liable to the CONTRACTOR for any such payments made
in good faith.
19.7 If the OWNER fails to make payment thirty (30) days after
approval by the ENGINEER, in addition to other remedies available to the
CONTRACTOR, there shall be added to each such payment interest at the maximum
legal rate commencing on the first day after said payment is due and continuing
until the payment is received by the CONTRACTOR.
20. ACCEPTANCE OF FINAL PAYMENT AS RELEASE
20.1 The acceptance by the CONTRACTOR of final payment shall be
and shall operate as a release to the OWNER of all claims and all liability to
the CONTRACTOR other than claims in stated amounts as may be specifically
excepted by the CONTRACTOR for all things done or furnished in connection with
this WORK and for every act and neglect of the OWNER and others relating to or
arising out of this WORK. Any payment, however, final or otherwise, shall not
release the CONTRACTOR or his sureties from any obligations under the CONTRACT
DOCUMENTS or the Performance BOND and Payment BONDS.
21. INSURANCE
21.1 The CONTRACTOR shall purchase and maintain such insurance as
will protect him from claims set forth below which may arise out of or result
from the CONTRACTOR'S execution of the WORK, whether such execution be by
himself or by any SUBCONTRACTOR or by anyone directly or indirectly employed by
any of them, or by anyone for whose acts any of them may be liable:
21.1.1 Claims under workmen's compensation disability benefit and
other similar employee benefit acts;
21.1.2 Claims for damages because of bodily injury, occupational
sickness or disease, or death of his employees;
21.1.3 Claim for damages because of bodily injury, sickness or
disease, or death of any person other than his employees;
21.1.4 Claims for damages insured by usual personal injury liability
coverage which are sustained (1) by any person as a result of an offense
directly or indirectly related to the employment of such person by the
CONTRACTOR, or (2) by any other person, and
21.1.5 Claims for damages because of injury to or destruction of
tangible property, including loss of use resulting therefrom.
21.2 Certificates of Insurance acceptable to the OWNER shall be
filed with the OWNER prior to commencement of the WORK. These Certificates
shall contain a provision that coverages afforded under the policies will not
be cancelled unless at least fifteen (15) days prior WRITTEN NOTICE has been
given to the OWNER.
21.3 The CONTRACTOR shall procure and maintain, at his own
expense, during the the CONTRACT TIME, liability insurance as hereinafter
specified:
21.3.1 CONTRACTOR'S General Public Liability and Property Damage
Insurance including vehicle coverage issued to the CONTRACTOR and protecting
him from all claims for destruction of or damage to property, arising out of or
in connection with any operations under the CONTRACT DOCUMENTS whether such
operations be by himself or by any SUBCONTRACTOR under him or anyone directly
or indirectly employed by the CONTRACTOR or by a SUBCONTRACTOR under him.
Insurance shall be written with a limit of liability of not less than $500,000
for all damages arising out of bodily injury including death, at any time
resulting therefrom, sustained by any one person in any one accident, and a
limit of liability of not less than $500,000 aggregate for any such damages
sustained by two or more persons in any one accident. Insurance shall be
written with a limit of liability of not less than $200,000 for all property
damage sustained by any one person in any one accident: and a limit of
liability of not less than $200,000 aggregate for any such damage sustained by
two or more persons in any one accident.
21.3.2 The CONTRACTOR shall acquire and maintain, if applicable, Fire
and Extended Coverage insurance upon the PROJECT to the full insurable value
thereof for the benefit of the OWNER, the CONTRACTOR, and SUBCONTRACTORS as
their interest may appear. This provision shall in no way release the
CONTRACTOR or CONTRACTOR'S surety from obligations under the CONTRACT DOCUMENTS
to fully complete the PROJECT.
21.4 The CONTRACTOR shall procure and maintain, at his own expense
during the CONTRACT TIME, in accordance with the provisions of the laws of the
state in which the work is performed, Workmen's Compensation Insurance
including occupational disease provisions, for all of his employees at the site
of the PROJECT and in case any work is sublet, the CONTRACTOR shall require
such SUBCONTRACTOR similarly to provide Workmen's Compensation Insurance,
including occupational disease provisions for all of the latter's employees
unless such employees are covered by the protection afforded by the
CONTRACTOR. In case any class of employees engaged in hazardous work under
this contract at the site of the PROJECT is not protected under Workmen's
Compensation statute, the CONTRACTOR shall provide, and shall cause each
SUBCONTRACTOR to provide, adequate and suitable insurance for the protection of
his employees not otherwise protected.
21.5 The CONTRACTOR shall secure, if applicable, "All
Risk" type Builder's Risk Insurance for WORK to be performed. Unless
specifically authorized by the OWNER, the amount of such insurance shall not be
less than the CONTRACT PRICE totaled in the BID. The policy shall cover not
less than the losses due to fire, explosion, hail, lightning, vandalism,
malicious mischief, wind, collapse, riot, aircraft, and smoke during the
CONTRACT TIME, and until the WORK is accepted by the OWNER. The policy shall
name the insured the CONTRACTOR, the ENGINEER, and the OWNER.
22. CONTRACT SECURITY
22.1 The CONTRACTOR shall within ten (10) days after the receipt
of the NOTICE OF AWARD furnish the OWNER with a Performance Bond and a Payment
Bond in penal sums equal to the amount of the CONTRACT PRICE conditioned upon
the performance by the CONTRACTOR of all undertakings, covenants, terms,
conditions, and agreements of the CONTRACT DOCUMENTS, and upon the prompt
payment by the CONTRACTOR to all persons supplying labor and materials in the
prosecution of the WORK provided by the CONTRACT DOCUMENTS. Such BONDS shall
be executed by the CONTRACTOR and a corporate bonding company licensed to
transact such business in the state in which the WORK is to be performed and
named on the current list of "Surety Companies Acceptable on Federal
Bonds" as published in the Treasury Department Circular Number 570. The
expense of these BONDS shall be borne by the CONTRACTOR. If at any time a
surety on any such BOND is declared a bankrupt or loses its right to do
business in the state in which the WORK is to be performed or is removed from
the list of Surety Companies accepted on Federal BONDS, CONTRACTOR shall within
ten (10) days after notice from the OWNER to do so, substitute an acceptable
BOND (or BONDS) in such form and sum and signed by such other surety or
sureties as may be satisfactory to the OWNER. The premiums on such BOND shall
be paid by the CONTRACTOR. No further payments shall be deemed due nor shall
be made until the new surety or sureties shall have furnished an acceptable
BOND to the OWNER.
23. ASSIGNMENTS
23.1 Neither the CONTRACTOR nor the OWNER shall sell, transfer,
assign or otherwise dispose of the Contract or any portion thereof, or of his
right, title or interest therein, or his obligations thereunder, without
written consent of the other party.
24. INDEMNIFICATION
24.1 The CONTRACTOR will indemnify and hold harmless the OWNER and
the ENGINEER and their agents and employees from and against all claims,
damages, losses and expenses including attorney's fees arising out of or
resulting from the performance of the WORK, provided that any such claims,
damage loss or expense is attributable to bodily injury, sickness, disease or
death, or to injury to or destruction of tangible property, including the loss
of use resulting therefrom; and is caused in whole or in part by any negligent
or willful act or omission of the CONTRACTOR, and SUBCONTRACTOR, anyone
directly or indirectly employed by any of them or anyone for whose acts any of
them may be liable.
24.2 In any and all claims against the OWNER or the ENGINEER, or
any of their agents or employees, by any employee of the CONTRACTOR, any
SUBCONTRACTOR, anyone directly or indirectly employed by any of them, or anyone
for whose acts any of them may be liable, the indemnification obligation shall
not be limited in any way by any limitation on the amount or type of damages,
compensation or benefits payable by or for the CONTRACTOR or any SUBCONTRACTOR
under workmen's compensation acts, disability benefit acts or other employee
benefits acts.
24.3 The obligation of the CONTRACTOR under this paragraph shall
not extend to the liability of the ENGINEER, his agents or employees arising
out of the preparation or approval of maps, DRAWINGS, opinions, reports,
surveys, CHANGE ORDERS, designs or SPECIFICATIONS.
25. SEPARATE CONTRACTS
25.1 The OWNER reserves the right to let other contracts in
connection with this PROJECT. The CONTRACTOR shall afford other CONTRACTORS
reasonable opportunity for the introduction and storage of their materials and
the execution of their WORK, and shall properly connect and coordinate his WORK
with theirs. If the proper execution or results of any part of the
CONTRACTOR'S WORK depends upon the WORK of any other CONTRACTOR, the CONTRACTOR
shall inspect and promptly report to the ENGINEER any defects in such WORK that
render it unsuitable for such proper execution and results.
25.2 The OWNER may perform additional WORK related to the PROJECT
by himself, or he may let other contracts containing provisions similar to
these. The CONTRACTOR will afford the other CONTRACTORS who are parties to
such Contracts (or the OWNER, if he is performing the additional WORK himself),
reasonable opportunity for the introduction and storage or materials and
equipment and the execution of WORK, and shall properly connect and coordinate
his WORK with theirs.
25.3 If the performance of additional WORK by other CONTRACTORS or
the OWNER is not noted in the CONTRACT DOCUMENTS prior to the execution of the
CONTRACT, written notice thereof shall be given to the CONTRACTOR prior to
starting any such additional WORK. If the CONTRACTOR believes that the
performance of such additional WORK by the OWNER or others involves him in
additional expense or entitles him to an extension of the CONTRACT TIME, he may
make a claim therefore as provided in Sections 14 and 15.
26. SUBCONTRACTING
26.1 The CONTRACTOR may utilize the services of specialty
SUBCONTRACTORS on those parts of the WORK which, under normal contracting
practices, are performed by specialty SUBCONTRACTORS.
26.2 The CONTRACTOR shall not award WORK to SUBCONTRACTOR(s), in
excess of fifty (50%) percent of the CONTRACT PRICE, without prior written
approval of the OWNER.
26.3 The CONTRACTOR shall be fully responsible to the OWNER for
the acts and omissions of his SUBCONTRACTORS, and of persons either directly or
indirectly employed by them, as he is for the acts and omissions of persons
directly employed by him.
26.4 The CONTRACTOR shall cause appropriate provisions to be
inserted in all subcontracts relative to the WORK to bind SUBCONTRACTORS to the
CONTRACTOR by the terms of the CONTRACT DOCUMENTS insofar as applicable to the
WORK of SUBCONTRACTORS and to give the CONTRACTOR the same power or regards
terminating any subcontract that the OWNER may exercise over the CONTRACTOR under
any provision of the CONTRACT DOCUMENTS.
26.5 Nothing contained in this CONTRACT shall create any contractual
relation between any SUBCONTRACTOR and the OWNER.
27. ENGINEER'S AUTHORITY
27.1 The ENGINEER shall act as the OWNER'S representative during
the construction period. He shall decide questions which may arise as to
quality and acceptability of materials furnished and WORK performed. He shall
interpret the intent of the CONTRACT DOCUMENTS in a fair and unbiased manner.
The ENGINEER will make visits to the site and determine if the WORK is
proceeding in accordance with the CONTRACT DOCUMENTS.
27.2 The CONTRACTOR will be held strictly to the intent of the
CONTRACT DOCUMENTS in regard to the quality of materials, workmanship and
execution of the WORK. Inspections may be made at the factory or fabrication
plant of the source of material supply.
27.3 The ENGINEER will not be responsible for the construction
means, control, techniques, sequences, procedures, or construction safety.
27.4 The ENGINEER shall promptly make the decisions relative to
interpretation of the CONTRACT DOCUMENTS.
28. LAND AND RIGHTS-OF-WAY
28.1 Prior to issuance of NOTICE TO PROCEED, the OWNER shall
obtain all land and rights-of-way necessary for carrying out and for the
completion of the WORK to be performed pursuant to the CONTRACT DOCUMENTS,
unless otherwise mutually agreed.
28.2 The OWNER shall provide to the CONTRACTOR information which
delineates and describes the lands owned and rights-of-way acquired.
28.3 The CONTRACTOR shall provide at his own expense and without
liability to the OWNER any additional land and access thereto that the
CONTRACTOR may desire for temporary construction facilities, or for storage of
materials.
29. GUARANTY
29.1 The CONTRACTOR shall guarantee all materials and equipment
furnished and WORK performed for a period of one (1) year from the date of
SUBSTANTIAL COMPLETION. The CONTRACTOR warrants and guarantees for a period of
one (1) year from the date of SUBSTANTIAL COMPLETION of the system that the
completed system if free from all defects due to faulty materials or
workmanship and the CONTRACTOR shall promptly make such corrections as may be
necessary by reason of such defects including the repairs of any damage to other
parts of the system resulting from such defects. The OWNER will give notice of
observed defects with reasonable promptness. In the event that the CONTRACTOR
should fail to make such repairs, adjustments, or other WORK that may be made
necessary by such defects, the OWNER may do so and charge the CONTRACTOR the
cost thereby incurred. The Performance BOND shall remain in full force and
effect through the guarantee period.
30. ARBITRATION
30.1 All claims, disputes and other matters in question arising out
of, or relating to, the CONTRACT DOCUMENTS or the breach thereof, except for
claims which have been waived by the making and acceptance of final payment as
provided by Section 20 shall be decided by arbitration in accordance with the
Construction Industry Arbitration Rules of the American Arbitration
Association. This agreement to arbitrate shall be specifically enforceable
under the prevailing arbitration law. The award rendered by the arbitrators
shall be final, and judgement may be entered upon it in any court having
jurisdiction thereof.
30.2 Notice of the demand for arbitration shall be filed in
writing with the other party to the CONTRACT DOCUMENTS and with the American
Arbitration Association, and a copy shall be filed with the ENGINEER. Demand
for arbitration shall in no event be made on any claim, dispute or other matter
in question which would be barred by the applicable statue of limitations.
30.3 The CONTRACTOR will carry on the WORK and maintain the
progress schedule during any arbitration proceedings, unless otherwise mutually
agreed in writing.
31. TAXES
31.1 The CONTRACTOR will pay all sales consumer use and other
similar taxes required by the law of the place where the WORK is performed.