35 Ill. Adm. Code 363.302
Consolidation of Priorities
Section 363
Section 363.302
Consolidation of Priorities
a) Notwithstanding Section 363.301, two or more needs of one or
more applicants which are initially ranked at different priorities, may be
consolidated into one need at the higher (highest) priority, and a grant may be
issued under this Subpart for the consolidated need at the higher (highest)
priority, if the following conditions are satisfied:
1) The applicant must have a facilities plan approved by the
Agency which concludes that the two or more needs will be most cost-effectively
met by an integrated solution; and
2) Available state and federal funding must be adequate to permit
complete funding of the consolidated need.
b) Such consolidations may include:
1) Sewer rehabilitation work and sewage treatment plant
improvements and/or intercepting sewer construction;
2) Projects to eliminate on-system wet weather overflow and
sewage treatment plant inprovements and/or intercepting sewer construction;
3) Projects to construct collection systems in currently
unsewered communities and projects to construct a new sewage treatment plant
and/or intercepting sewer.