35 Ill. Adm. Code 364.403

F5 Factor

Year: 2026Length: 98 wordsOfficial source
Section 364 Section 364.403  F5 Factor a)         F5 is a factor which is added for those projects whose priority position is to be retained. b)         The value of F5 will be retained only if the value of the quanitity F1 x F2 x F3 x F6 x F4 is greater than the corresponding quantity for the lowest priority need which has an F5 value greater than zero.  If the value of this quantity does not meet this test, F5 for the need will be reduced to zero following the completion of facility planning and subsequent determination of F6.