35 Ill. Adm. Code 365.320
Project Plan
Section 365.320 Project Plan
a) Loan
applicants shall submit to the Agency a Project Plan, with its initial Funding
Nomination Form, that shall consist of plans and studies that are directly
related to the construction or implementation of the proposed project. The
Project Plan shall provide documentation on the need for the project for which
loan assistance is being requested.
b) Planning
previously or collaterally accomplished under local, State or federal programs
may be utilized to the extent applicable. If any information required to be
furnished as part of a Project Plan has been developed separately, it shall be
furnished and incorporated by reference in the Project Plan.
c) When
applicable, the loan applicant shall also submit drafts of any
intergovernmental agreements or demonstrations of legal authority necessary for
project implementation.
d) The Project Plan may
include more than one construction project.
e) The Project Plan shall
include the following supporting data:
1) A
complete description of the selected wastewater treatment system or other
systems, identification of any existing violations of federal or State regulations,
and identification of the needs to be addressed by the proposed project;
2) A
discussion of the technical, financial, managerial, and environmental
considerations that form the basis for the loan applicant's selection of the
recommended project, including an evaluation regarding the elimination of
infiltration and inflow if applicable. When appropriate to the project scope,
the following issues shall be addressed:
A) The
relationship of the capacity of the selected alternative to the needs to be served,
including reserve capacity;
B) Identification
of current and proposed effluent discharge limitations and water quality
standards for the proposed treatment works or facilities, as required by Title
IV of the CWA and 35 Ill. Adm. Code: Subtitle C;
C) A
discussion of the operational requirements for the selected alternative and
provisions for the ultimate disposal of sludge materials from the wastewater
treatment process;
D) An
inventory of the relative environmental impacts of the selected alternative and
a discussion of the measures that would be required during design and
construction to mitigate or minimize negative environmental impacts; and
E) Adequate
basis of design information for the selected alternative to confirm the
reasonability of cost estimates;
3) A
detailed description of the alternative selected for loan assistance, including
preliminary engineering data, complete cost estimates for design and
construction, one or more 8.5 by 11 inch site map or maps locating areas of
construction and indirect impacts, and a projected schedule for completion.
The engineering data shall include, to the extent appropriate, flow diagrams,
unit process descriptions, detention times, flow rates, unit capacities, etc.,
sufficient to demonstrate that the project proposed will be designed in
accordance with 35 Ill. Adm. Code 370;
4) Any
required comments or approvals from relevant federal, State, interstate,
regional or local agencies;
5) An
implementation plan for the proposed recommendations, including necessary
financial arrangements for the operation and maintenance of the project and
repayment of the proposed loan amount, as well as the impact of these costs on
the system users; and
6) Information
sufficient to support a determination as to whether any portion of the project
addresses green infrastructure, energy efficient improvements, or other
environmentally innovative activities.
f) Planning for Individual
Systems
1) Construction
involving privately owned residential wastewater treatment works must be part
of the cost-effective solution in the approved Project Plan.
2) Loan
applicants must have legal authority to access all such privately owned systems
at all reasonable times for such purposes as inspections, monitoring, building,
operation, maintenance, rehabilitation, and replacement.
g) The
Project Plan will be reviewed by the Agency under the State environmental
review process specified in Section 365.330. If substantial changes are made to
the project scope following submittal to the Agency, the Project Plan shall be
revised or amended and resubmitted for review and approval.
h) In the Project Plan, a
public loan applicant must certify:
1) it
has studied and evaluated the cost and effectiveness of the processes,
materials, techniques, and technologies for carrying out the proposed project
or activity for which assistance is sought; and
2) it
has selected, to the maximum extent practicable, a project or activity that
maximizes the potential for efficient water use, reuse, recapture, and
conservation, and energy conservation, taking into account:
A) the cost of constructing
the project or activity;
B) the
cost of operating and maintaining the project or activity over the life of the
project or activity; and
C) the
cost of replacing the project or activity.