35 Ill. Adm. Code 367.630
Final Phase II and LQMP Reports
Section 367
Section 367.630 Final Phase
II and LQMP Reports
Lake owners with Phase II or
LQMP projects shall carry out a limited lake monitoring program for at least
one year after all protection or restoration practices have been implemented.
This program, as specified and agreed upon with the Agency in the final Phase I
report, shall be conducted to allow for an evaluation of pre- and
post-implementation lake conditions. Upon completion of the
post-implementation monitoring program, the lake owner shall prepare a final
report that discusses project implementation and results. The final report
shall, at a minimum, include the topics and be organized according to the
following format, and shall be submitted to the Agency on the date established
in the financial assistance agreement:
a) An Executive Summary section;
b) An Introduction section;
c) A Materials and Methods section, including the following:
1) A description of the implementation program, including both
watershed and in-lake treatments implemented;
2) A description of pre- and post-implementation water quality
sampling and analysis procedures, including:
A) physiochemical and limnological data collection;
B) chlorophyll and phytoplankton data collection; and
C) other applicable data collection;
3) A description of the methods used to calculate a hydrologic
budget;
4) A description of the methods used to calculate a nutrient
budget;
5) A description of the methods used to calculate a sediment
budget;
6) A description of data analysis procedures, including how data
were grouped into pre- and post-implementation periods and how data were
analyzed;
d) A Results and Discussion section, including:
1) An analysis of the watershed implementation program;
2) An analysis of the in-lake implementation program pertaining
to:
A) dissolved oxygen and temperature;
B) alkalinity, pH and conductivity;
C) Secchi transparency and suspended solids;
D) nutrients;
E) chlorophyll;
F) phytoplankton; and
G) other applicable parameters;
3) An analysis of pre- and post-implementation hydrologic
budgets;
4) An analysis of pre- and post-implementation nutrient budgets;
and
5) An analysis of pre- and post-implementation sediment budgets;
e) A Conclusions and Recommendations section;
f) A References section;
g) An Appendices section.