35 Ill. Adm. Code 370.APPENDIX C

C Table No. 3 – Air Test Table for Sanitary Sewer Leakage Testing*

Last amended: 1997Year: 2026Length: 214 wordsOfficial source
Section 370.APPENDIX C   Table No. 3 – Air Test Table for Sanitary Sewer Leakage Testing* SPECIFICATION TIME (MIN:SEC) REQUIRED FOR PRESSURE DROP FROM 3½ TO 2½ PSIG WHEN TESTING ONE PIPE DIAMETER ONLY Length of Sewer Pipe In Feet PIPE DIAMETER, INCHES 4 6 8 10 12 15 18 21 24 25 0:04 0:10 0:28 0:28 0:40 1:02 1:29 2:01 2:38 50 0:09 0:20 0:35 0:55 1:19 2:04 2:58 4:03 5:17 75 0:13 0:30 0:53 1:23 1:59 3:06 4:27 6:04 7:55 100 0:18 0:40 1:10 1:50 2:38 4:08 5:56 8:05 10:34 125 0:22 0:50 1:28 2:18 3:18 5:09 7:26 9:55 11:20 150 0:26 0:59 1:46 2:45 3:58 6:11 8:30 175 0:31 1:09 2:03 3:13 4:37 7:05 200 0:35 1:19 2:21 3:40 5:17 12:06 225 0:40 1:29 2:38 4:08 5:40 10:25 13:36 250 0:44 1:39 2:56 4:35 8:31 11:35 15:07 275 0:48 1:49 3:14 4:43 9:21 12:44 16:38 300 0:53 1:59 3:31 10:12 13:53 18:09 350 1:02 2:19 3:47 8:16 11:54 16:12 21.10 400 1:10 2:38 6:03 9:27 13:36 18:31 24:12 450 1:19 2:50 6:48 10:38 15:19 20:50 27:13 500 1:28 5:14 7:34 11:49 17:01 23:09 30:14 *From Standard Specifications for Water and Sewer Main Construction in Illinois, Fourth Edition, May, 1986.  (Copies may be obtained from Illinois Society of Professional Engineers, Springfield, Illinois 62704.)
35 Ill. Adm. Code 370.APPENDIX C: C Table No. 3 – Air Test Table for Sanitary Sewer Leakage Testing* | Justis AI