35 Ill. Adm. Code 371.167
Maintenance Management
Section 371
Section 371.167 Maintenance Management
This element of PO must identify necessary actions and
related implementation schedules for establishing an adequate maintenance
management system. Personnel responsible for the completion of each action must
be identified by name and title. Reference must be made to the chapter on
maintenance in the O&M Manual.
ACTION
START
DATE
END
DATE
RESPONSIBLE
PERSONNEL
a)
Complete the inventories for spare parts and necessary
tools.
b)
Assemble the manufacturers' manuals and any other
equipment literature.
c)
Train the maintenance staff on equipment maintenance.
d)
Acquire lubricants for equipment.
e)
Begin the pre-start-up maintenance schedule.
f)
Review the maintenance management program with the
maintenance staff.