35 Ill. Adm. Code 375.403
Field Studies
Section 375
Section 375.403 Field
Studies
a) First flush volumes may be determined through direct field
measurement at a point of overflow, modeling of the collection system or
equally accurate techniques. Either approach is dependent on a field
monitoring program as described in (c) below. Commonly, first flush for the
design storm is determined by direct measurement of flush rate and volume for
several storms of varying intensity and extrapolating to the design storm (1.2
in/hr.).
b) Detailed monitoring may be limited to less than the total number
of overflow locations in the system when monitoring all locations would be
impossible or would not be helpful in demonstrating the capabilities of the
system. Sampling sites should be selected in order to monitor the largest
discharges in terms of loading. Consideration shall also be given to the
different land use patterns, population densities, and sewer system
characteristics tributary to a given overflow site within the study area.
c) General guidance for field measurement includes:
1) A minimum of 3 storms should be monitored for each sampling
site.
2) There shall be a least one rain gauge located within the study
area. For systems serving an area of over 2 squares miles, multiple gauges
shall be used and located to achieve gauge spacing of 2 miles or less
throughout the study area. Rain gauges should be on the continuous recording
type, otherwise manual readings should be recorded on intervals of 10 minutes
or less. If only one gauge is used it should be located near the center of the
study area; multiple gauges shall be located so as to identify variations in
storm intensity across the study area.
3) Flow monitoring shall be initiated at the onset of a storm and
continue through and beyond the sewer flushing period. Flow meters may be located
in interceptor manholes, diversion structures, outfall sewers or other
locations where dependable operation is assured. Caution should be taken to
protect instrumentation from flooding, corrosion, excess humidity, vandalism or
other factors which jeopardize either the equipment or reliability of the data.
4) Water samples should be collected at the onset of the storm
and at 10 or 15 minute intervals thereafter. In most instances a moderate to
heavy storm will fully flush the system within two hours. Most automatic
discrete samplers have adequate capacity to contain the entire flush period
with 10 minutes sampling frequency. Again, caution should be taken to protect
against flooding, corrosion, or excess humidity that may cause malfunctioning
or failure of the mechanical or electronic components of the sampler. Samples
should be analyzed for BOD
5
as defined in 35 Ill. Adm. Code
304.120(a), total and volatile suspended solids with sample preservation, and
analysis consistent with Standard Methods 15
th
Edition (1980).
5) Overflow points that are not subject to direct flow and
quality monitoring should be inspected during the storm period to determine if
the overflows are functioning and to estimate the rate and duration of
overflow.