35 Ill. Adm. Code 506.311
Additional Design and Construction Standards for Construction in a Flood Fringe Area
Section 506
Section 506.311Â Additional
Design and Construction Standards for Construction in a Flood Fringe Area
No new non-lagoon livestock
management facility or livestock waste handling facility may be constructed
within the floodway of a 100-year floodplain. A new livestock management
facility or livestock waste handling facility may be constructed within the portion
of a 100-year floodplain that is within the flood fringe and outside the
floodway
if
the facility is designed and constructed to be protected
from flooding and meets the requirements set forth in the Rivers, Lakes, and
Streams Act
[615 ILCS 5],
Section 5-40001 of the Counties Code
[55
ILCS 5/5-40001],
and executive order number 4 (1979).
[510 ILCS
77/13(b)(1)]Â Despite the other requirements of this Subpart or 8 Ill. Adm.
Code 900, the following criteria must be incorporated into the design of a
non-lagoon livestock management facility or livestock waste handling facility
proposed for construction in the flood fringe of a 100-year floodplain:
a)Â Â Â Â Â Â Â Â The berms and walls must be designed and constructed to
withstand the hydrostatic pressures from flood waters that may be exerted on
the berms and walls during a flood event;
b)Â Â Â Â Â Â Â Â The elevation of the lowest point on the berm top and wall must
be at the elevation of the 100-year flood plus a minimum of two feet;
c)Â Â Â Â Â Â Â Â For facilities with unequal length and width dimensions, the
facility must be oriented with the longest dimension parallel to the expected
direction of floodwater flow; and
d)Â Â Â Â Â Â Â Â The owner or operator of the livestock waste handling facility
may, upon written request and with written approval from the Department, modify
or exceed these standards to meet site specific objectives. The owner or
operator must demonstrate that such modification will be at least as protective
of the groundwater, the surface water, and the structural integrity of the
livestock waste handling facility as the requirements of this Part.