SECTION 611.922 SYSTEM-SPECIFIC STUDIES
Section 611.922
System-Specific Studies
a) System-Specific
Study Plan. A supplier's system-specific study plan must be based on either
existing monitoring results, as required under subsection (a)(1), or modeling,
as required under subsection (a)(2). The supplier must prepare and submit the
supplier's system-specific study plan to the Agency according to the schedule
in Section 611.920(c).
1) Existing
Monitoring Results. A supplier may comply by submitting monitoring results
collected before it is required to begin monitoring under Section 611.920(c).
The monitoring results and analysis must meet the criteria in subsections
(a)(1)(A) and (a)(1)(B).
A) Minimum
Requirements
i) TTHM
and HAA5 results must be based on samples collected and analyzed in compliance
with Section 611.381. Samples must be collected no earlier than five years
prior to the study plan submission date.
ii) The
monitoring locations and frequency must meet the conditions identified in the
applicable of subsections (a)(1)(A)(iii) through (a)(1)(A)(xv). Each location
must be sampled once during the peak historical month for TTHM levels or HAA5
levels or the month of warmest water temperature for every 12 months of data
submitted for that location. Monitoring results must include all Subpart I
compliance monitoring results, plus additional monitoring results as necessary
to meet minimum sample requirements.
iii) A
Subpart B system supplier that serves fewer than 500 persons must collect
samples from three monitoring locations: three samples for TTHM and three
samples for HAA5.
iv) A
Subpart B system supplier that serves 500 to 3,300 persons must collect samples
from three monitoring locations: nine samples for TTHM and nine samples for
HAA5.
v) A
Subpart B system supplier that serves 3,301 to 9,999 persons must collect
samples from six monitoring locations: 36 samples for TTHM and 36 samples for
HAA5.
vi) A
Subpart B system supplier that serves 10,000 to 49,999 persons must collect
samples from each of 12 monitoring locations: 72 samples for TTHM and 72
samples for HAA5.
vii) A
Subpart B system supplier that serves 50,000 to 249,999 persons must collect
samples from 24 monitoring locations: 144 samples for TTHM and 144 samples for
HAA5.
viii) A Subpart
B system supplier that serves 250,000 to 999,999 persons must collect samples
from 36 monitoring locations: 216 samples for TTHM and 216 samples for HAA5.
ix) A
Subpart B system supplier that serves 1,000,000 to 4,999,999 persons must
collect samples from 48 monitoring locations: 288 samples for TTHM and 288
samples for HAA5.
x) A
Subpart B system supplier that serves 5,000,000 or more persons must collect
samples from 60 monitoring locations: 360 samples for TTHM and 360 samples for
HAA5.
xi) A
groundwater system supplier that serves fewer than 500 persons must collect
samples from three monitoring locations: three samples for TTHM and three
samples for HAA5.
xii) A
groundwater system supplier that serves 500 to 9,999 persons must collect samples
from three monitoring locations: nine samples for TTHM and nine samples for
HAA5.
xiii) A
groundwater system supplier that serves 10,000 to 99,999 persons must collect
samples from 12 monitoring locations: 48 samples for TTHM and 48 samples for
HAA5.
xiv) A
groundwater system supplier that serves 100,000 to 499,999 persons must collect
samples from 18 monitoring locations: 72 samples for TTHM and 72 samples for
HAA5.
xv) A
groundwater system supplier that serves 500,000 or more persons must collect
samples from 24 monitoring locations: 96 samples for TTHM and 96 samples for
HAA5.
B) Reporting
Monitoring Results. A supplier must report the following information:
i) The
supplier must report previously collected monitoring results and certify that
the reported monitoring results include all compliance and noncompliance
results generated during the time period that began with the first reported
result and that ended with the most recent Subpart I results;
ii) The
supplier must certify that the samples were representative of the entire
distribution system and treatment and that the distribution system and
treatment have not changed significantly since the samples were collected;
iii) The
supplier's study monitoring plan must include a schematic of its distribution
system (including distribution system entry points and their sources and
storage facilities in the system), with notes indicating the locations and
dates of all completed or planned system-specific study monitoring;
iv) The
supplier's system-specific study plan must specify the population served and
its system type (i.e., that it is a Subpart B or groundwater system);
v) The
supplier must keep a complete copy of its system-specific study plan submitted
under this subsection (a)(1), including any Agency modification of the supplier's
system-specific study plan, for as long as the supplier is required to keep its
IDSE report under subsection (b)(5); and
vi) If
the supplier submits previously collected data that fully meet the number of
samples required under subsection (a)(1)(A)(ii), and the Agency rejects some of
the data in writing, by a SEP, the supplier must either conduct additional
monitoring to replace rejected data on a schedule approved by the Agency in the
SEP, or it must conduct standard monitoring under Section 611.921.
2) Modeling.
A supplier may comply through analysis of an extended-period simulation
hydraulic model. The extended-period simulation hydraulic model and analysis
must meet the following criteria:
A) Minimum
Extended-Period Hydraulic Model Requirements
i) The extended-period
hydraulic model must simulate 24-hour variation in demand and show a
consistently repeating 24-hour pattern of residence time.
ii) The extended-period
hydraulic model must represent the criteria listed in subsection (a)(2)(D).
BOARD NOTE: This subsection
(a)(2)(A)(ii) is derived from 40 CFR 141.602(a)(2)(i)(B). The Board has
codified 40 CFR 141.602(a)(2)(i)(B)(
1
) through (a)(2)(i)(B)(
9
) as
subsections (a)(2)(D)(i) through (a)(2)(D)(ix) to comport with Illinois
Administrative Code codification requirements.
iii) The extended-period
hydraulic model must be calibrated or have calibration plans for the current
configuration of the distribution system during the period of high TTHM
formation potential. All storage facilities in the system must be evaluated as
part of the calibration process. All required calibration must be completed no
later than 12 months after the supplier has submitted the plan.
B) Reporting
Modeling. The supplier's system-specific study plan must include the
information described in subsections (a)(2)(B)(i) through (a)(2)(B)(vii),
subject to the requirements of subsection (a)(2)(B)(vii).
i) Tabular
or spreadsheet data demonstrating that the model meets requirements in
subsections (a)(2)(A)(ii) and (a)(2)(D).
ii) A
description of all calibration activities undertaken and, if calibration is
complete, a graph of predicted tank levels versus measured tank levels for the
system storage facility with the highest residence time in each pressure zone,
and a time
-
series graph of the residence time at the longest residence
time storage facility in the distribution system showing the predictions for
the entire simulation period (i.e., from time zero until the time it takes for
the model to reach a consistently repeating pattern of residence time).
iii) Model
output showing preliminary 24-hour average residence time predictions
throughout the distribution system.
iv) The
timing and the number of samples representative of the distribution system
planned for at least one monitoring period of TTHM and HAA5 dual-sample
monitoring at a number of locations no fewer than would be required for the
system under standard monitoring in Section 611.921 during the historical month
of high TTHM. These samples must be taken at locations other than existing
Subpart I compliance monitoring locations.
v) A
description of how all requirements will be completed no later than 12 months
after the supplier submits the supplier's system-specific study plan.
vi) A
schematic of the supplier's distribution system (including distribution system
entry points and their sources and system storage facilities), with notes
indicating the locations and dates of all completed system-specific study
monitoring (if calibration is complete) and all Subpart I compliance monitoring.
vii) The
population served and system type (i.e., that it is a Subpart B or groundwater
system).
viii) The
supplier must keep a complete copy of the supplier's system-specific study plan
submitted under this subsection (a)(2), including any Agency modification of
the supplier's system-specific study plan, for as long as the supplier is
required to keep the supplier's IDSE report under subsection (b)(7).
C) If the
supplier submits a model that does not fully meet the requirements under
subsection (a)(2), the supplier must correct the Agency-cited deficiencies and
respond to Agency inquiries concerning the model. If the supplier fails to
correct deficiencies or respond to inquiries to the Agency's satisfaction, the
supplier must conduct standard monitoring under Section 611.921.
D) The extended-period
hydraulic model must represent the following criteria:
i) 75
percent of pipe volume;
ii) 50
percent of pipe length;
iii) All
pressure zones;
iv) All
12-inch diameter and larger pipes;
v) All
eight-inch and larger pipes that connect pressure zones, influence zones from
different sources, storage facilities, major demand areas, pumps, and control
valves or that are known or expected to be significant conveyors of water;
vi) All
six-inch and larger pipes that connect remote areas of a distribution system to
the main portion of the system;
vii) All
storage facilities with standard operations represented in the model;
viii) All
active pump stations with controls represented in the model; and
ix) All
active control valves.
BOARD NOTE: This subsection
(a)(2)(D) is derived from 40 CFR 141.602(a)(2)(i)(B). The Board has codified
40 CFR 141.602(a)(2)(i)(B)(
1
) through (a)(2)(i)(B)(
9
) as
subsections (a)(2)(D)(i) through (a)(2)(D)(ix) to comport with Illinois
Administrative Code codification requirements.
b) IDSE Report.
The supplier's IDSE report must include the elements required in subsections
(b)(1) through (b)(6). The supplier must submit its IDSE report according to
the applicable of the schedules in Section 611.920(c).
1) The
supplier's IDSE report must include all TTHM and HAA5 analytical results from
Subpart I compliance monitoring and all system-specific study monitoring
conducted during the period of the system-specific study presented in a tabular
or spreadsheet format acceptable to the Agency. If changed from the supplier's
system-specific study plan submitted under subsection (a), the supplier's IDSE
report must also include a schematic of its distribution system, the population
served, and system type (i.e., that it is a Subpart B or groundwater system).
2) If
the supplier used the modeling provision under subsection (a)(2), it must
include final information for the elements described in subsection (a)(2)(B),
and a 24-hour time-series graph of residence time for each Subpart Y compliance
monitoring location selected.
3) The
supplier must recommend and justify Subpart Y compliance monitoring locations
and timing based on the protocol in Section 611.925.
4) The
supplier's IDSE report must include an explanation of any deviations from its
approved system-specific study plan.
5) The
supplier's IDSE report must include the basis (analytical and modeling results)
and justification that it used to select the recommended Subpart Y monitoring
locations.
6) The
supplier may submit its IDSE report in lieu of its system-specific study plan
on the schedule identified in Section 611.920(c) for submission of the
system-specific study plan if the supplier believes that it has the necessary
information before the time that the system-specific study plan is due. If the
supplier elects this approach, its IDSE report must also include all
information required under subsection (a).
7) The
supplier must keep a complete copy of its IDSE report submitted under this Section
for ten years after the date that the supplier submitted its IDSE report. If
the Agency modifies the Subpart Y monitoring requirements that the supplier
recommended in the supplier's IDSE report or if the Agency approves alternative
monitoring locations, the supplier must keep a copy of the Agency's
notification on file for ten years after the date of the Agency's
notification. The supplier must make the IDSE report and any Agency
notification available for review by the Agency or the public.
BOARD NOTE: Derived from 40 CFR
141.602.