Project Plan
Section 662.320 Project Plan
a) Loan applicants
shall submit to the Agency a Project Plan, with its initial Funding Nomination
Form, that shall consist of plans and studies that are directly related to the
construction or implementation of the proposed project. The Project Plan shall
provide documentation on the need for the project for which loan assistance is
being requested.
b) Planning
previously or collaterally accomplished under local, State or federal programs
may be utilized to the extent applicable. If any information required to be
furnished as part of a Project Plan has been developed separately, it shall be
furnished and incorporated by reference in the Project Plan.
c) When applicable,
the loan applicant shall also submit drafts of any intergovernmental agreements
or demonstrations of legal authority necessary for project implementation.
d) The Project Plan
may include more than one construction project.
e) The Project Plan
shall include the following supporting data:
1) A complete
description of the selected public water supply or other systems,
identification of any existing violations of federal or State regulations, and
identification of the needs to be addressed by the proposed project;
2) A discussion of
the technical, financial, managerial, and environmental considerations that
form the basis for the loan applicant's selection of the recommended project.
When appropriate to the project scope, the following issues shall be addressed:
A) The relationship
of the capacity of the selected alternative to the needs to be served,
including reserve capacity;
B) A discussion of
the operational requirements for the selected alternative and provisions for
the ultimate disposal of waste by-products in accordance with State requirements;
C) An inventory of
the relative environmental impacts of the selected alternative and a discussion
of the measures that would be required during design and construction to
mitigate or minimize negative environmental impacts; and
D) Adequate basis of
design information for the selected alternative to confirm the reasonability of
cost estimates;
3) A detailed
description of the alternative selected for loan assistance, including
preliminary engineering data, complete cost estimates for design and
construction, one or more 8.5 by 11 inch site map or maps locating areas of
construction and indirect impacts, and a projected schedule for completion.
The engineering data shall include, to the extent appropriate, flow diagrams,
unit process descriptions, detention times, flow rates, unit capacities, etc.,
sufficient to demonstrate that the project proposed will be designed in
accordance with 35 Ill. Adm. Code Subtitle F;
4) Any required
comments or approvals from relevant federal, State, interstate, regional or
local agencies;
5) An
implementation plan for the proposed recommendations, including necessary
financial arrangements for the operation and maintenance of the project and
repayment of the proposed loan amount, as well as the impact of these costs on
the system users; and
6) Information
sufficient to support a determination as to whether any portion of the project
addresses green infrastructure, energy efficient improvements, or other
environmentally innovative activities.
f) The Project Plan
will be reviewed by the Agency under the State environmental review process
specified in Section 662.330. If substantial changes are made to the project
scope following submittal to the Agency, the Project Plan shall be revised or