35 Ill. Adm. Code 611.952
Additional Watershed Control Requirements for Unfiltered Systems
Section 611.952 Additional
Watershed Control Requirements for Unfiltered Systems
a) Applicability. A
Subpart B system supplier that serves fewer than 10,000 persons that does not
provide filtration must continue to comply with all of the filtration avoidance
criteria in Sections 611.211 and 611.230 through 611.233, as well as the
additional watershed control requirements in subsection (b).
b) Requirements to Avoid
Filtration. A supplier must take any additional steps necessary to minimize
the potential for contamination by Cryptosporidium oocysts in the source
water. A watershed control program must fulfill the following for
Cryptosporidium:
1) The program must
identify watershed characteristics and activities that may have an adverse effect
on source water quality; and
2) The program must monitor
the occurrence of activities that may have an adverse effect on source water
quality.
c) Determination of Adequacy
of Control Requirements. During an onsite inspection conducted under the provisions
of Section 611.232(c), the Agency must determine whether a watershed control
program is adequate to limit potential contamination by Cryptosporidium
oocysts. The adequacy of the program must be based on the comprehensiveness of
the watershed review; the effectiveness of the program to monitor and control
detrimental activities occurring in the watershed; and the extent to which the
supplier has maximized land ownership or controlled land use within the
watershed.