35 Ill. Adm. Code 670.205
Agency Review and Confirmation of Certification
Section 670
Section 670.205 Agency
Review and Confirmation of Certification
Upon receipt of a
certification pursuant to
Section 670.203,
the Agency shall, within 90
days, take one of the following actions
:
a)
Notify the owner of the site in writing that the certification
is complete and adequate
;
b)
Notify the owner of the site in writing that the
certification is not adequate, including a statement of the reasons therefor
;
c)
Notify the owner of the site in writing that a site
inspection will be held within 120 days, and that following such inspection but
still within the 120 day period further action will be taken pursuant to
subsections (a) and (b) of this Section;
d)
Notify in writing the owner of the site that pursuant to
Section
17.1 of the Act
a county or municipality is conducting a
groundwater protection needs assessment or the Agency is conducting a well site
survey which encompasses the site for which certification is being processed,
and specify a time period, not to exceed a total of 180 days from the date of
the notice, for consideration of the findings from such assessment or survey
and by which further action will be taken pursuant to
subsections (a) and
(b) of this Section. (Section 14.5(c) of the Act)