35 Ill. Adm. Code 702.152
Reporting Requirements
Section 702
Section 702.152 Reporting
Requirements
a) Planned Changes. The permittee must give notice to the Agency
as soon as possible of any planned physical alterations or additions to the
permitted facility.
b) Anticipated Noncompliance. The permittee must give advance
notice to the Agency of any planned changes in the permitted facility or
activity that may result in noncompliance with permit requirements. For RCRA,
see also 35 Ill. Adm. Code 703.247.
c) Transfers. This permit is not transferable to any person,
except after notice to the Agency. The Agency may require modification of the
permit to change the name of the permittee and incorporate such other
requirements as may be necessary under the appropriate Act. (See Sections
702.182 and 702.183, in some cases modification is mandatory.)
d) Monitoring Reports. Monitoring results must be reported at
the intervals specified in the permit.
e) Compliance Schedules. Reports of compliance or non-compliance
with, or any progress reports on, interim and final requirements contained in
any compliance schedule of the permit must be submitted no later than specified
in Section 702.162.
f) Twenty-four hour reporting as required in 35 Ill. Adm. Code
703.245 or 704.181(d).
g) Other Noncompliance. The permittee must report all instances
of noncompliance not reported under subsections (d), (e), and (f) at the time
monitoring reports are submitted. The reports must contain the information
referenced in subsection (f).
h) Other Information. If the permittee becomes aware that it
failed to submit any relevant facts in a permit application or that it submitted
incorrect information in a permit application or in any report to the Agency, the
permittee must promptly submit such facts or information.
BOARD NOTE: Derived from 40 CFR
144.51(l) and 270.30(l).