35 Ill. Adm. Code 703.150
Application by Existing HWM Facilities and Interim Status Qualifications
Section 703
Section 703.150 Application
by Existing HWM Facilities and Interim Status Qualifications
a) The owner or operator of an existing HWM facility or of an HWM
facility in existence on the effective date of statutory or regulatory
amendments that render the facility subject to the requirement to have a RCRA
permit must submit Part A of the permit application to the Agency no later than
the following times, whichever comes first:
1) Six months after the date of publication of regulations that
first require the owner or operator to comply with standards in 35 Ill. Adm.
Code 725 or 726; or
2) Thirty days after the date the owner or operator first becomes
subject to the standards in 35 Ill. Adm. Code 725 or 726.
b) In granting a variance under subsection (c), the Board will
consider whether there has been substantial confusion as to whether the owner or
operator of such facilities were required to file a Part A application and
whether such confusion was attributable to ambiguities in 35 Ill. Adm. Code
720, 721, or 725.
c) The time for filing Part A of the permit application may be
extended only by a Board Order entered pursuant to a variance petition.
d) The owner or operator of an existing HWM facility may be
required to submit Part B of the permit application. The Agency will notify
the owner or operator that a Part B application is required, and set a date for
receipt of the application, not less than six months after the date the notice
is sent. The owner or operator my voluntarily submit a Part B application for
all or part of the HWM facility at any time. Notwithstanding the above, any
owner or operator of an existing HWM facility must submit a Part B permit
application in accordance with the dates specified in Section 703.157. Any
owner or operator of a land disposal facility in existence on the effective
date of statutory or regulatory amendments that render the facility subject to
the requirement to have a RCRA permit must submit a Part B application in
accordance with the dates specified in Section 703.157.
e) Interim
status may be terminated as provided in Section 703.157.
BOARD NOTE:
Derived from 40 CFR 270.10(e)(2017).