35 Ill. Adm. Code 704.188
Plugging and Abandonment
Section 704
Section 704.188 Plugging and
Abandonment
Any permit must include a
requirement that, after a cessation of operations of two years, the owner or
operator must plug and abandon the well in accordance with the plan unless it
does the following:
a) It provides notice to the Agency; and
b) It describes actions or procedures satisfactory to the Agency
that the owner or operator will take to ensure that the well will not endanger
USDWs during the period of temporary abandonment. These actions and procedures
must include compliance with the technical requirements applicable to active
injection wells, unless waived by the Agency.
BOARD NOTE:
Derived from 40 CFR 144.52(a)(6) (2005).