35 Ill. Adm. Code 705.126
Decision Schedule
Section 705
Section 705.126 Decision
Schedule
For each permit application from
a major new HWM facility or major new UIC injection well, the Agency must, no
later than the effective date of the application, prepare and mail to the
applicant a projected decision schedule. The schedule must specify target
dates by which the Agency intends to do the following:
a) Prepare
a draft permit pursuant to Subpart C;
b) Give
public notice pursuant to Subpart D;
c) Complete the public comment period, including any public
hearing pursuant to Subpart E; and
d) Issue a final permit pursuant to Subpart F.
BOARD NOTE: Derived from 40 CFR
124.3(g) (2017).