35 Ill. Adm. Code 705.126

Decision Schedule

Last amended: 2018Year: 2026Length: 108 wordsOfficial source
Section 705 Section 705.126  Decision Schedule For each permit application from a major new HWM facility or major new UIC injection well, the Agency must, no later than the effective date of the application, prepare and mail to the applicant a projected decision schedule.  The schedule must specify target dates by which the Agency intends to do the following: a)         Prepare a draft permit pursuant to Subpart C; b)         Give public notice pursuant to Subpart D; c)         Complete the public comment period, including any public hearing pursuant to Subpart E; and d)         Issue a final permit pursuant to Subpart F. BOARD NOTE:  Derived from 40 CFR 124.3(g) (2017).