35 Ill. Adm. Code 722.365
Emergency Procedures
Section
722.365
Emergency Procedures
a) Whenever there is an imminent
or actual emergency situation, the emergency coordinator (or his designee when
the emergency coordinator is on call) must immediately undertake the following
actions:
1) Activate internal facility
alarms or communication systems, where applicable, to notify all facility
personnel; and
2) Notify appropriate state or
local agencies with designated response roles if their help is needed.
b) Whenever there is a release,
fire, or explosion, the emergency coordinator must immediately identify the
character, exact source, amount, and areal extent of any released materials.
The emergency coordinator may do this by observation or review of the facility
records or manifests and, if necessary, by chemical analysis.
c) Concurrently, the emergency
coordinator must assess possible hazards to human health or the environment
that may result from the release, fire, or explosion. This assessment must
consider both direct and indirect effects of the release, fire, or explosion (e.g.,
the effects of any toxic, irritating, or asphyxiating gases that are generated,
the effects of any hazardous surface water run-offs from water or chemical
agents used to control fire and heat-induced explosions, etc.).
d) If the emergency coordinator
determines that the facility has had a release, fire, or explosion which could
threaten human health or the environment outside the facility, the emergency
coordinator must report the findings as follows:
1) If the assessment indicates
that evacuation of local areas may be advisable, the emergency coordinator must
immediately notify appropriate local authorities. The emergency coordinator
must be available to help appropriate officials decide whether local areas should
be evacuated; and
2) The emergency coordinator must
immediately notify either the government official designated as the on-scene
coordinator for that geographical area or the
National
Response Center
(using their 24-hour toll free number 800/424–8802). The
report must include:
A) The name and telephone number of
the reporter;
B) The name and address of the
generator;
C) The time and type of incident (e.g.,
release, fire, etc.);
D) The name and quantity of
materials involved, to the extent known;
E) The extent of injuries, if any;
and
F) The possible hazards to human
health or the environment outside the facility.
e) During an emergency, the
emergency coordinator must take all reasonable measures necessary to ensure
that fires, explosions, and releases do not occur, recur, or spread to other
hazardous waste at the generator's facility. These measures must include,
where applicable, stopping processes and operations, collecting and containing
released hazardous waste, and removing or isolating containers.
f) If the generator stops
operations in response to a fire, explosion, or release, the emergency
coordinator must monitor for leaks, pressure buildup, gas generation, or
ruptures in valves, pipes, or other equipment, wherever this is appropriate.
g) Immediately after an emergency,
the emergency coordinator must provide for treating, storing, or disposing of
recovered waste, contaminated soil or surface water, or any other material that
results from a release, fire, or explosion at the facility. Unless the
generator can demonstrate, in accordance with 35 Ill. Adm. Code 721.103(c) or
(d), that the recovered material is not a hazardous waste, then it is a newly
generated hazardous waste that must be managed in accordance with all the applicable
requirements and conditions for exemption in 35 Ill. Adm. Code 722, 723, and
725.
h) The emergency coordinator must
ensure that the following is true in the affected areas of the facility:
1) No hazardous waste that may be
incompatible with the released material is treated, stored, or disposed of
until cleanup procedures are completed; and
2) All emergency equipment listed
in the contingency plan is cleaned and fit for its intended use before
operations are resumed.
i) The generator must note in the
operating record the time, date, and details of any incident that requires
implementing the contingency plan. Within 15 days after the incident, the
generator must submit a written report on the incident to the Agency. The report
must include the following information:
1) The name, address, and
telephone number of the generator;
2) The date, time, and type of
incident (e.g., fire, explosion, etc.);
3) The name and quantity of
materials involved;
4) The extent of injuries, if any;
5) An assessment of actual or
potential hazards to human health or the environment, where this is applicable;
and
6) The estimated quantity and
disposition of recovered material that resulted from the incident.