35 Ill. Adm. Code 724.322
Action Leakage Rate
Section 724
Section 724.322Â Action
Leakage Rate
a)Â Â Â Â Â Â Â Â The Agency must approve an action leakage rate for surface
impoundment units subject to Section 724.321(c) or (d). The action leakage
rate is the maximum design flow rate that the LDS can remove without the fluid
head on the bottom liner exceeding 1 foot. The action leakage rate must
include an adequate safety margin to allow for uncertainties in the design
(e.g., slope, hydraulic conductivity, thickness of drainage material, etc.),
construction, operation, and location of the LDS, waste and leachate
characteristics, likelihood and amounts of other sources of liquids in the LDS,
and proposed response actions (e.g., the action leakage rate must consider
decreases in the flow capacity of the system over time resulting from siltation
and clogging, rib layover and creep of synthetic components of the system,
overburden pressures, etc.).
b)Â Â Â Â Â Â Â Â To determine if the action leakage rate has been exceeded, the
owner or operator must convert the weekly or monthly flow rate from the
monitoring data obtained under Section 724.326(d) to an average daily flow rate
(gallons per acre per day) for each sump. The average daily flow rate for each
sump must be calculated weekly during the active life and closure period and,
if the unit is closed in accordance with Section 724.328(b), monthly during the
post-closure care period, unless the Agency approves a different frequency
pursuant to Section 724.326(d).