35 Ill. Adm. Code 725.295
Inspections
Section 725
Section 725.295Â Inspections
a)Â Â Â Â Â Â Â Â The
owner or operator must inspect the following, where present, at least once each
operating day, data gathered from monitoring and leak detection equipment
(e.g., pressure or temperature gauges, monitoring wells, etc.) to ensure that
the tank system is being operated according to its design.
b)Â Â Â Â Â Â Â Â Except
as noted under subsection (c), the owner or operator must inspect the following
at least once each operating day:
1)Â Â Â Â Â Â Â Â Overfill/spill control equipment (e.g., waste-feed cutoff
systems, bypass systems, and drainage systems) to ensure that it is in good
working order;
2)Â Â Â Â Â Â Â Â Above ground portions of the tank system, if any, to detect
corrosion or releases of waste; and
3)Â Â Â Â Â Â Â Â The construction materials and the area immediately
surrounding the externally accessible portion of the tank system, including the
secondary containment system (e.g., dikes) to detect erosion or signs of
releases of hazardous waste (e.g., wet spots, dead vegetation, etc.).
BOARD NOTE:Â
Section 725.115(c) requires the owner or operator to remedy any deterioration
or malfunction the owner or operator finds. Section 725.296 requires the owner
or operator to notify the Agency within 24 hours of confirming a release.Â
Also, federal 40 CFR 302Â may require the owner or operator to notify the
National Response Center of a release.
c)Â Â Â Â Â Â Â Â The
owner or operator of a tank system that either uses leak detection equipment to
alert facility personnel to leaks or implements established workplace practices
to ensure leaks are promptly identified must inspect at least weekly those
areas described in subsections (b)(1) through (b)(3). Use of the alternate
inspection schedule must be documented in the facility's operating record.Â
This documentation must include a description of the established workplace
practices at the facility.
d)Â Â Â Â Â Â Â Â This
subsection (d) corresponds with 40 CFR 265.195(d), which USEPA has removed and
marked "reserved". This statement maintains structural consistency
with the corresponding federal requirements.
e)Â Â Â Â Â Â Â Â Ancillary equipment that is not provided with secondary
containment, as described in Section 725.293(f)(1) through (f)(4), must be
inspected at least once each operating day.
f)Â Â Â Â Â Â Â Â The owner or operator must inspect cathodic protection
systems, if present, according to, at a minimum, the following schedule to
ensure that they are functioning properly:
1)Â Â Â Â Â Â Â Â The proper operation of the cathodic protection system must be
confirmed within six months after initial installation, and annually
thereafter; and
2)Â Â Â Â Â Â Â Â All sources of impressed current must be inspected or tested,
as appropriate, at least every other month.
BOARD NOTE:Â
The practices described in "Control of External Corrosion on Metallic
Buried, Partially Buried, or Submerged Liquid Storage Systems", NACE
Recommended Practice RP0285-85, or "Cathodic Protection of Underground
Petroleum Storage Tanks and Piping Systems", API Recommended Practice
1632, each incorporated by reference in 35 Ill. Adm. Code 720.111(a), may be
used, where applicable, as guidelines in maintaining and inspecting cathodic
protection systems.
g)Â Â Â Â Â Â Â Â The owner or operator must document in the operating record of
the facility an inspection of those items in subsections (a) and (b).