35 Ill. Adm. Code 725.297
Closure and Post-Closure Care
Section 725
Section 725.297Â Closure and
Post-Closure Care
a)Â Â Â Â Â Â Â Â At closure of a tank system, the owner or operator must remove
or decontaminate all waste residues, contaminated containment system components
(liners, etc.), contaminated soils and structures and equipment contaminated
with waste, and manage them as hazardous waste, unless 35 Ill. Adm. Code
721.103(d) applies. The closure plan, closure activities, cost estimates for
closure, and financial responsibility for tank systems must meet all of the
requirements specified in Subparts G and H.
b)Â Â Â Â Â Â Â Â If the owner or operator demonstrates that not all
contaminated soils can be practicably removed or decontaminated as required in
subsection (a), then the owner or operator must close the tank system and
perform post-closure care in accordance with the closure and post-closure care
requirements that apply to landfills (Section 725.410). In addition, for the
purposes of closure, post-closure and financial responsibility, such a tank
system is then considered to be a landfill, and the owner or operator must meet
all of the requirements of landfills specified in Subparts G and H.
c)Â Â Â Â Â Â Â Â If an owner or operator has a tank system that does not have
secondary containment that meets the requirements of Section 725.293(b) through
(f), and which is not exempt from the secondary containment requirements in
accordance with Section 725.293(g), then the following requirements apply:
1)Â Â Â Â Â Â Â Â The closure plan for the tank system must include both a plan
for complying with subsection (a), and a contingent plan for complying with
subsection (b);
2)Â Â Â Â Â Â Â Â A contingent post-closure plan for complying with subsection
(b) must be prepared and submitted as part of the permit application;
3)Â Â Â Â Â Â Â Â The cost estimates calculated for closure and post-closure
care must reflect the costs of complying with the contingent closure plan and
the contingent post-closure plan, if these costs are greater than the costs of
complying with the closure plan prepared for the expected closure under
subsection (a);
4)Â Â Â Â Â Â Â Â Financial assurance must be based on the cost estimates in
subsection (c)(3); and
5)Â Â Â Â Â Â Â Â For the purposes of the contingent closure and post-closure
plans, such a tank system is considered to be a landfill, and the contingent
plans must meet all of the closure, post-closure care, and financial
responsibility requirements for landfills under Subparts G and H.