35 Ill. Adm. Code 730.186
Injection Well Construction Requirements
Section 730.186 Injection Well Construction Requirements
a) General.
The owner or operator must ensure that its Class VI injection wells are
constructed and completed to fulfill the following requirements:
1) The
well construction and completion must prevent the movement of fluids into or
between USDWs or into any unauthorized zone;
2) The
well construction and completion must permit the use of appropriate testing
devices and workover tools; and
3) The
well construction and completion must permit continuous monitoring of the
annulus space between the injection tubing and long-string casing.
b) Casing and cementing of
Class VI injection wells.
1) The
casing, cement, and other materials used in the construction of each Class VI
injection well must have sufficient structural strength and be designed to last
for the life of the geologic sequestration project. All well materials must be
compatible with fluids with which the materials may be expected to come into
contact, and the owner or operator must submit sufficient documentation to the
Agency to support a determination that the casing, cement, and other materials
meet or exceed standards developed for these materials by the American
Petroleum Institute, ASTM International, or a comparable industry standards
organization. The casing and cementing program must be designed to prevent the
movement of fluids into or between USDWs. In order to allow the Agency to
determine and specify casing and cementing requirements, the owner or operator
must provide the following information to the Agency:
A) The depth to the
injection zones;
B) The
injection pressure, external pressure, internal pressure, and axial loading;
C) The hole size;
D) The
size and grade of all casing strings (the wall thickness, external diameter,
nominal weight, length, joint specification, and construction material);
E) The
corrosiveness of the carbon dioxide stream and formation fluids;
F) The down-hole
temperatures;
G) The lithology of the
injection and confining zones;
H) The type or grade of
cement and cement additives; and
I) The
quantity, chemical composition, and temperature of the carbon dioxide stream.
2) The
surface casing must extend through the base of the lowermost USDW and be
cemented to the surface through the use of a single or multiple strings of
casing and cement.
3) At
least one long-string casing, using a sufficient number of centralizers, must
extend to the injection zone and must be cemented by circulating cement to the
surface in one or more stages.
4) The
circulation of cement may be accomplished by staging. The Agency must approve
an alternative method of cementing when it determines that the cement cannot be
recirculated to the surface, provided the owner or operator can demonstrate, by
using logs, that the cement does not allow fluid movement behind the well bore.
5) The
cement and cement additives must be compatible with the carbon dioxide stream
and formation fluids and of sufficient quality and quantity to maintain
integrity over the design life of the geologic sequestration project. The
integrity and location of the cement must be verified that uses technology
capable of evaluating cement quality radially and which identifies the location
of channels to ensure that USDWs are not endangered.
c) Tubing and packer.
1) The
tubing and packer materials used in the construction of a Class VI injection
well must be compatible with fluids with which the materials may be expected to
come into contact, and the owner or operator must submit sufficient
documentation to the Agency to support a determination that the tubing and
packer meet or exceed standards developed for these materials by the American
Petroleum Institute, ASTM International, or a comparable industry standards
organization.
2) The
owner or operator of a Class VI injection well must inject fluids through
tubing with a packer set at a depth opposite a cemented interval at the
location approved by the Agency.
3) In
order for the Agency to determine and specify requirements for tubing and
packer, the owner or operator must submit the following information to the
Agency:
A) The depth of setting;
B) The
characteristics of the carbon dioxide stream (the chemical content,
corrosiveness, temperature, and density) and formation fluids;
C) The maximum proposed
injection pressure;
D) The maximum proposed
annular pressure;
E) The
proposed injection rate (intermittent or continuous) and the volume or mass of
the carbon dioxide stream;
F) The size of the tubing
and casing; and
G) The tubing tensile,
burst, and collapse strengths.
BOARD NOTE: This Section
corresponds with 40 CFR 146.86 (2011).