35 Ill. Adm. Code 731.166
Corrective Action Plan
Section 731
Section 731.166 Corrective
Action Plan
a) At any point after reviewing the information submitted in
compliance with Sections 731.161 through 731.163, the Agency may require owners
and operators to submit additional information or to develop and submit a
corrective action plan for responding to contaminated soils and groundwater. If
a plan is required, owners and operators must submit the plan according to a
schedule and format established by the Agency. Alternatively, owners and
operators may, after fulfilling the requirements of Sections 731.161 through
731.163, choose to submit a corrective action plan for responding to contaminated
soil and groundwater.
b) The Agency must approve the corrective action plan only after
ensuring that implementation of the plan will adequately protect human health,
safety and the environment. In making this determination, the Agency must
consider the following factors as appropriate:
1) The physical and chemical characteristics of the regulated
substance, including its toxicity, persistence and potential for migration;
2) The hydrogeologic characteristics of the facility and the
surrounding area;
3) The proximity quality and current and future uses of nearby
surface water and groundwater;
4) The potential effects of residual contamination on nearby
surface water and groundwater;
5) An exposure assessment; and
6) Any information assembled in compliance with this Subpart.
c) Upon approval of the corrective action plan or as directed by
the Agency, owners and operators must implement the plan, including
modifications to the plan made by the Agency. They must monitor, evaluate and
report the results of implementing the plan in accordance with a schedule and
in a format established by the Agency.
d) Owners and operators may, in the interest of minimizing
environmental contamination and promoting more effective cleanup, begin cleanup
of soil and groundwater before the corrective action plan is approved provided
that they:
1) Notify the Agency of their intention to begin cleanup;
2) Comply with any conditions imposed by the Agency, including
halting cleanup or mitigating adverse consequences from cleanup activities; and
3) Incorporate these self-initiated cleanup measures in the
corrective action plan that is submitted to the Agency.