35 Ill. Adm. Code 734.430
Monitoring Well Construction and Sampling
Section 734.430 Monitoring Well Construction and
Sampling
a) At a
minimum, all monitoring well construction must satisfy the following
requirements:
1) Wells
must be constructed in a manner that will enable the collection of representative
groundwater samples;
2) Wells
must be cased in a manner that maintains the integrity of the borehole. Casing
material must be inert so as not to affect the water sample. Casing requiring
solvent-cement type couplings must not be used;
3) Wells
must be screened to allow sampling only at the desired interval. Annular space
between the borehole wall and well screen section must be packed with clean,
well-rounded and uniform material sized to avoid clogging by the material in
the zone being monitored. The slot size of the screen must be designed to
minimize clogging. Screens must be fabricated from material that is inert with
respect to the constituents of the groundwater to be sampled;
4) Annular
space above the well screen section must be sealed with a relatively
impermeable, expandable material such as cement/bentonite grout that does not
react with or in any way affect the sample, in order to prevent contamination
of groundwater samples and groundwater and avoid interconnections. The seal
must extend to the highest known seasonal groundwater level;
5) The
annular space must be backfilled with expanding cement grout from an elevation
below the frost line and mounded above the surface and sloped away from the
casing so as to divert surface water away;
6) Wells
must be covered with vented caps and equipped with devices to protect against
tampering and damage. Locations of wells must be clearly marked and protected
against damage from vehicular traffic or other activities associated with expected
site use; and
7) Wells
must be developed to allow free entry of groundwater, minimize turbidity of the
sample, and minimize clogging.
b) Monitoring
well construction diagrams must be completed for each monitoring well. The
well construction diagrams must be submitted in the corresponding site
investigation plan, site investigation completion report, or corrective action
completion report on forms prescribed and provided by the Agency and, if
specified by the Agency in writing, in an electronic format.
c) Static
groundwater elevations in each well must be determined and recorded following
well construction and prior to each sample collection to determine the gradient
of the groundwater table, and must be reported in the corresponding site
investigation plan, site investigation completion report or corrective action
completion report.