35 Ill. Adm. Code 734.605
Applications for Payment
Section 734.605 Applications for Payment
a) An
owner or operator seeking payment from the Fund must submit to the Agency an
application for payment on forms prescribed and provided by the Agency and, if
specified by the Agency by written notice, in an electronic format. The owner
or operator may submit an application for partial payment or final payment.
Costs for which payment is sought must be approved in a budget, provided,
however, that no budget must be required for early action activities conducted
pursuant to Subpart B of this Part other than free product removal activities
conducted more than 45 days after confirmation of the presence of free product.
b) A complete application
for payment must consist of the following elements:
1) A
certification from a Licensed Professional Engineer or a Licensed Professional
Geologist acknowledged by the owner or operator that the work performed has
been in accordance with a technical plan approved by the Agency or, for early
action activities, in accordance with Subpart B of this Part;
2) A
statement of the amounts approved in the corresponding budget and the amounts
actually sought for payment along with a certified statement by the owner or
operator that the amounts so sought have been expended in conformance with the
elements of a budget approved by the Agency;
3) A
copy of the OSFM or Agency eligibility and deductibility determination;
4) Proof
that approval of the payment requested will not exceed the limitations set
forth in the Act and Section 734.620 of this Part;
5) A
federal taxpayer identification number and legal status disclosure
certification;
6) Private insurance
coverage form(s);
7) A minority/women's
business form;
8) Designation
of the address to which payment and notice of final action on the application
for payment are to be sent;
9) An
accounting of all costs, including but not limited to, invoices, receipts, and
supporting documentation showing the dates and descriptions of the work
performed; and
10) Proof
of payment of subcontractor costs for which handling charges are requested.
Proof of payment may include cancelled checks, lien waivers, or affidavits from
the subcontractor.
c) The
address designated on the application for payment may be changed only by
subsequent notification to the Agency, on a form provided by the Agency, of a
change in address.
d) Applications
for payment and change of address forms must be mailed or delivered to the
address designated by the Agency. The Agency's record of the date of receipt must
be deemed conclusive unless a contrary date is proven by a dated, signed
receipt from certified or registered mail.
e) Applications
for partial or final payment may be submitted no more frequently than once
every 90 days.
f) Except
for applications for payment for costs of early action conducted pursuant to
Subpart B of this Part, other than costs associated with free product removal
activities conducted more than 45 days after confirmation of the presence of
free product, in no case must the Agency review an application for payment
unless there is an approved budget on file corresponding to the application for
payment.
g) In
no case must the Agency authorize payment to an owner or operator in amounts
greater than the amounts approved by the Agency in a corresponding budget.
Revised cost estimates or increased costs resulting from revised procedures
must be submitted to the Agency for review in accordance with Subpart E of this
Part using amended budgets plans as required under this Part.
h) Applications
for payment of costs associated with a Stage 1, Stage 2, or Stage 3 site
investigation may not be submitted prior to the approval or modification of a
site investigation plan for the next stage of the site investigation or the
site investigation completion report, whichever is applicable.
i) Applications
for payment of costs associated with site investigation or corrective action
that was deferred pursuant to Section 734.450 of this Part may not be submitted
prior to approval or modification of the corresponding site investigation plan,
site investigation completion report, or corrective action completion report.
j) All
applications for payment of corrective action costs must be submitted no later
than one year after the date the Agency issues a No Further Remediation Letter
pursuant to Subpart G of this Part. For releases for which the Agency issued a
No Further Remediation Letter prior to March 1, 2006, all applications for
payment must be submitted no later than March 1, 2007.